3545 N COPELAND PL 90032

Certificate Information: 3545 N COPELAND PL 90032

Application / Permit
21047-10000-00598
Plan Check / Job No.
B21LA04932
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
(N) SPA & SWIMMING POOL APPROX 16' X 38'-6" INCL. SPA PER ENGINEER DESIGN SEE COMMENTS *****
Permit Issued
Issued on 5/20/2021
Issuing Office
Current Status
CofO Issued on 2/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/16/2021 APPLICANT
Assigned to Plan Check Engineer 3/18/2021 SERGIO GUTIERREZ
Corrections Issued 3/26/2021 SERGIO GUTIERREZ
Quality Review Completed 4/1/2021 KEN GILL
Plan Check Approved 5/6/2021 SERGIO GUTIERREZ
Issued 5/20/2021 APPLICANT
Building Plans Picked Up 5/26/2021 APPLICANT
CofO in Progress 2/2/2022 OSVALDO PARAMO
CofO in Progress 2/2/2022 OSVALDO PARAMO
Permit Finaled 2/14/2022 DEROLD HAUFF
CofO Issued 2/14/2022 DEROLD HAUFF
Permit Finaled 2/14/2022 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/23/2021 BRIAN MILLER
GPI Written Notices Cleared 5/6/2021 SERGIO GUTIERREZ

Contact Information

Architect Obnial,, Cezar V; Lic. No.: C12189 39998 QUIGLEY ROAD      MURRIETA, CA 92562
Contractor Owner-Builder       ,
Engineer Evangelista,, Gil Viernes; Lic. No.: S2422 749 N FEATHERWOOD DR      DIAMOND BAR, CA 91765

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/29/2021 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 7/8/2021 Approved OSVALDO PARAMO
Pool Piping 7/8/2021 Approved OSVALDO PARAMO
Deputy Shotcrete 7/15/2021 Approved COREY HUPP
Gunite 7/15/2021 Not Ready for Inspection COREY HUPP
Deck 7/16/2021 Approved OSVALDO PARAMO
Enclosure/Fence 8/17/2021 Not Ready for Inspection COREY HUPP
Enclosure/Fence 8/27/2021 Approved OSVALDO PARAMO
Gas Piping or Gas Test 8/27/2021 Approved OSVALDO PARAMO
Equipment Noise Level 9/10/2021 Approved ROBERT CHAVEZ
Final 9/30/2021 Not Ready for Inspection COREY HUPP
SGSOV-Seismic Gas S/O Valve 9/30/2021 SGSOV Not Ready COREY HUPP
Final 10/15/2021 Corrections Issued COREY HUPP
SGSOV-Seismic Gas S/O Valve 10/15/2021 SGSOV Not Required COREY HUPP
Final 2/1/2022 OK to Issue CofO OSVALDO PARAMO