7561 S WESTLAWN AVE 90045
Certificate Information: 7561 S WESTLAWN AVE 90045
- Application / Permit
- 21047-10000-00507
- Plan Check / Job No.
- B21LA04155
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- 6'6" X 10'0" SPA AT REAR OF DWELLING. per city standard plan # 268 and engr details #551
- Permit Issued
- Issued on 5/7/2021
- Issuing Office
- Current Status
- CofO Issued on 12/13/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/9/2021 | STANLEY RAAP |
| Corrections Issued | 3/9/2021 | STANLEY RAAP |
| Applicant returned to address corrections | 3/23/2021 | LUKE GONZALES |
| Plan Check Approved | 4/29/2021 | SINA KHOSRAVI |
| Issued | 5/7/2021 | APPLICANT |
| Building Plans Picked Up | 5/11/2021 | APPLICANT |
| Permit Closed-Status Void | 12/1/2021 | BOBBY KEY |
| Re-Activate Permit | 12/7/2021 | BOBBY KEY |
| CofO in Progress | 12/7/2021 | KENNETH NAGLE |
| Permit Finaled | 12/13/2021 | DANIEL ORRANTE |
| CofO Issued | 12/13/2021 | DANIEL ORRANTE |
| Permit Finaled | 12/13/2021 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/29/2021 | STANLEY RAAP |
Contact Information
| Contractor | Varsity Pool & Spa Inc; Lic. No.: 861841-C53 | 449 WEST FOOTHILL BLVD #463 GLENDORA, CA 91741 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/18/2021 | Approved | ANTHONY MCDOWALL |
| Grounding or Bonding | 6/18/2021 | Approved | ANTHONY MCDOWALL |
| Pool Piping | 6/18/2021 | Corrections Issued | ANTHONY MCDOWALL |
| Pre-Gunite | 6/18/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Rough-Electrical | 6/18/2021 | Partial Approval | ANTHONY MCDOWALL |
| Pool Piping | 6/22/2021 | Approved | BRENDAN LOONEY |
| Enclosure/Fence | 10/14/2021 | Corrections Issued | DEANDRE HOFFMAN |
| Enclosure/Fence | 10/21/2021 | Approved | JOHN KAYON |
| Final | 11/18/2021 | Corrections Issued | ENRIQUE MIRELES |
| Pre-Gunite | 11/18/2021 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 11/18/2021 | SGSOV Approved | ENRIQUE MIRELES |
| Grading Pre-Inspection | 11/23/2021 | Partial Approval | JOHN KAYON |
| Final | 12/1/2021 | OK to Issue CofO | BOBBY KEY |