2190 N LINDA FLORA DR 90077
Certificate Information: 2190 N LINDA FLORA DR 90077
- Application / Permit
- 21047-10000-00504
- Plan Check / Job No.
- B21LA04145
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW SWIMMING POOL ON CASSIONS
- Permit Issued
- Issued on 12/27/2021
- Issuing Office
- Current Status
- CofO Issued on 6/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2021 | STARR CHEN |
| Corrections Issued | 3/22/2021 | STARR CHEN |
| Quality Review Completed | 3/27/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 5/14/2021 | STARR CHEN |
| Applicant returned to address corrections | 7/23/2021 | STARR CHEN |
| Applicant returned to address corrections | 8/26/2021 | STARR CHEN |
| Applicant returned to address corrections | 9/24/2021 | STARR CHEN |
| Plan Check Approved | 10/21/2021 | STARR CHEN |
| Issued | 12/27/2021 | APPLICANT |
| Building Plans Picked Up | 1/6/2022 | APPLICANT |
| CofO in Progress | 5/22/2024 | CARLOS MATAMOROS |
| Permit Finaled | 6/5/2024 | DANIEL ORRANTE |
| CofO Issued | 6/5/2024 | DANIEL ORRANTE |
| Permit Finaled | 6/5/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 10/21/2021 | STARR CHEN |
| Grading Pre-Inspection | Cleared | 10/21/2021 | STARR CHEN |
Contact Information
| Contractor | Structure Home; Lic. No.: 721043-B | 21860 BURBANK BLVD STE 110 WOODLAND HILLS, CA 91367 |
| Engineer | Babayan,, Raffi Samuel; Lic. No.: C72168 | 7718 DAY STREET LOS ANGELES, CA 91042 |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 3600 WILSHIRE BLVD STE 1903 LOS ANGELES, CA 90010 |
| Geologist | Cugno,, Giuseppe; Lic. No.: EG1804 | 1461 E CHEVY CHASE DR 200 BYER GEOTECHNICAL, INC. GLENDALE, CA 91206 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Other (see comments) | 5/3/2022 | Conditional Approval | CARLOS MATAMOROS |
| Pre-Inspection | 5/13/2022 | No Access for Inspection | CHRISTOPHER WILSON |
| Piling/Pier/Caisson | 6/7/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 6/8/2022 | Partial Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 6/27/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Grounding or Bonding | 7/5/2022 | Approved | CARLOS MATAMOROS |
| Pool Piping | 7/5/2022 | Approved | CARLOS MATAMOROS |
| Pre-Gunite | 7/5/2022 | Corrections Issued | CARLOS MATAMOROS |
| Deputy Other (see comments) | 7/21/2022 | Conditional Approval | CARLOS MATAMOROS |
| Gas Piping or Gas Test | 5/3/2023 | Approved | CARLOS MATAMOROS |
| Enclosure/Fence | 9/19/2023 | Approved | CARLOS MATAMOROS |
| Pool Equipment Noise Test | 9/28/2023 | Approved | ANDEY CHAPARRO |
| Excavation/Setback/Form/Re-Bar | 10/12/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Final | 10/12/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Pre-Gunite | 10/12/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 10/12/2023 | SGSOV Not Ready | CHRISTOPHER WILSON |
| Special/Order Compliance | 12/4/2023 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Final | 5/16/2024 | Approved | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 5/16/2024 | Approved | CARLOS MATAMOROS |
| Final | 5/16/2024 | OK to Issue CofO | CARLOS MATAMOROS |
| Pre-Gunite | 5/16/2024 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 5/16/2024 | SGSOV Approved | CARLOS MATAMOROS |