300 S SANTA FE AVE 90012
Certificate Information: 300 S SANTA FE AVE 90012
- Application / Permit
- 21047-10000-00493
- Plan Check / Job No.
- B21LA04080
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- Apartment
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- UCT SWIMMING POOL AND DETACHED SPA.
- Permit Issued
- Issued on 1/4/2022
- Issuing Office
- Current Status
- CofO Issued on 9/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2021 | JOE VO |
| Corrections Issued | 4/12/2021 | JOE VO |
| Quality Review Completed | 4/30/2021 | MICHAEL PEREZ |
| Plan Check Approved | 12/2/2021 | JOE VO |
| Issued | 1/4/2022 | APPLICANT |
| Building Plans Picked Up | 1/4/2022 | APPLICANT |
| CofO in Progress | 9/25/2023 | RAFAEL ESPINOZA |
| CofO Issued | 9/25/2023 | ERNESTO CORRAL |
| Permit Finaled | 9/25/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| DAS Clearance | Cleared | 12/1/2021 | EDDIE GARIN |
| Public Swimming Pool approval | Cleared | 12/2/2021 | LACDHS APPROVED |
Contact Information
| Contractor | Sunset Pools And Spas Inc; Lic. No.: 473735-C53 | 1400 E KATELLA AVE STE 217 ORANGE, CA 92867 |
Inspector Information
| RONALD JIMENEZ, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| LARRY ARNICK, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEY BUCHANAN, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| ERNESTO CORRAL, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL ESPINOZA, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/16/2022 | Corrections Issued | MARK FERRARI |
| Pre-Gunite | 8/17/2022 | Partial Inspection | MARK FERRARI |
| Pool Piping | 12/5/2022 | Not Ready for Inspection | MARK FERRARI |
| Pre-Gunite | 12/5/2022 | Not Ready for Inspection | MARK FERRARI |
| Rough-Electrical | 12/5/2022 | Not Ready for Inspection | MARK FERRARI |
| Rough-Plumbing | 12/5/2022 | Not Ready for Inspection | MARK FERRARI |
| Grounding or Bonding | 12/7/2022 | Not Ready for Inspection | MARK FERRARI |
| Pool Piping | 12/7/2022 | Not Ready for Inspection | MARK FERRARI |
| Pre-Gunite | 12/7/2022 | Partial Inspection | MARK FERRARI |
| Rough-Electrical | 12/7/2022 | Not Ready for Inspection | MARK FERRARI |
| Rough-Plumbing | 12/7/2022 | Not Ready for Inspection | MARK FERRARI |
| Gunite | 12/20/2022 | Partial Approval | JEROME BLACKWOOD |
| Deck | 5/15/2023 | Approved | JULIAN CAPUCETTI |
| Final | 5/15/2023 | Not Ready for Inspection | JULIAN CAPUCETTI |
| SGSOV-Seismic Gas S/O Valve | 5/15/2023 | SGSOV Not Ready | JULIAN CAPUCETTI |
| Final | 8/8/2023 | Not Ready for Inspection | RAFAEL ESPINOZA |
| SGSOV-Seismic Gas S/O Valve | 8/8/2023 | SGSOV Approved | RAFAEL ESPINOZA |
| Final | 8/21/2023 | Partial Inspection | RAFAEL ESPINOZA |
| Final | 9/25/2023 | OK to Issue CofO | RAFAEL ESPINOZA |