5240 N DAHLIA DR 90041

Certificate Information: 5240 N DAHLIA DR 90041

Application / Permit
21047-10000-00482
Plan Check / Job No.
B21LA03934
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 36'x12' POOL AND SPA PER STANDARD PLAN #268
Permit Issued
Issued on 7/7/2021
Issuing Office
Current Status
CofO Issued on 8/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/4/2021 APPLICANT
Assigned to Plan Check Engineer 3/9/2021 RACHEL BEYENE
Corrections Issued 3/9/2021 RACHEL BEYENE
Applicant returned to address corrections 5/18/2021 RICARDO RAMIREZ
Building Plans Picked Up 5/21/2021 APPLICANT
Plan Check Approved 6/30/2021 GEORGE ALVAREZ
Issued 7/7/2021 APPLICANT
CofO in Progress 8/2/2022 CRAIG VAUGHAN
Permit Finaled 8/11/2022 DEROLD HAUFF
CofO Issued 8/11/2022 DEROLD HAUFF
Permit Finaled 8/11/2022 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/30/2021 RAHEL BEYENE

Contact Information

Contractor Crystal Clear Pool & Spa Inc; Lic. No.: 805833-C53 P O BOX 299      MONROVIA, CA 91017
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 9/13/2021 Corrections Issued CRAIG VAUGHAN
Rough-Electrical 9/13/2021 Not Ready for Inspection CRAIG VAUGHAN
Rough-Plumbing 9/13/2021 Not Ready for Inspection CRAIG VAUGHAN
Pre-Gunite 9/23/2021 Not Ready for Inspection CRAIG VAUGHAN
Rough-Electrical 9/23/2021 Approved CRAIG VAUGHAN
Rough-Plumbing 9/23/2021 Not Ready for Inspection CRAIG VAUGHAN
Pre-Gunite 9/24/2021 Approved CRAIG VAUGHAN
Deputy Shotcrete 9/29/2021 No Access for Inspection CRAIG VAUGHAN
Deck 10/29/2021 Approved COREY HUPP
Enclosure/Fence 12/29/2021 Not Ready for Inspection CRAIG VAUGHAN
Enclosure/Fence 1/4/2022 Approved CRAIG VAUGHAN
Final 1/28/2022 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 1/28/2022 SGSOV Not Ready CRAIG VAUGHAN
Final 2/7/2022 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 2/7/2022 SGSOV Approved CRAIG VAUGHAN
Final 8/1/2022 OK to Issue CofO CRAIG VAUGHAN