1262 N SHADYBROOK DR 90210

Certificate Information: 1262 N SHADYBROOK DR 90210

Application / Permit
21047-10000-00466
Plan Check / Job No.
B21LA03790
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW POOL AND SPA 32' X 16' (SPA FLUSH INSIDE POOL)
Permit Issued
Issued on 1/13/2022
Issuing Office
Current Status
CofO Issued on 9/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/2/2021 APPLICANT
Assigned to Plan Check Engineer 3/4/2021 SINA KHOSRAVI
Corrections Issued 3/5/2021 SINA KHOSRAVI
Building Plans Picked Up 3/10/2021 APPLICANT
Plan Check Approved 1/12/2022 JOSEPH RAFOLS
Issued 1/13/2022 APPLICANT
CofO in Progress 9/11/2024 SEAN HAUPT
Permit Finaled 9/16/2024 RICHARD STEINBACH
CofO Issued 9/16/2024 RICHARD STEINBACH
Permit Finaled 9/16/2024 RICHARD STEINBACH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/9/2021 SINA KHOSRAVI
Construction within easement Cleared 12/3/2021 WALTER RAMIREZ
Miscellaneous Cleared 12/21/2021 JENSON LEE
Eng Process Fee Ord 176,300 Cleared 1/4/2022 JENSON LEE

Contact Information

Contractor Intex Design And Construction Inc; Lic. No.: 981718-B 15021 VENTURA BLVD STE 520      SHERMAN OAKS, CA 91403
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 4/14/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 4/15/2022 Approved CHRISTOPHER WILSON
Grounding or Bonding 4/15/2022 Partial Approval CHRISTOPHER WILSON
Pool Piping 4/15/2022 Approved CHRISTOPHER WILSON
Pre-Gunite 4/15/2022 Approved CHRISTOPHER WILSON
Rough-Electrical 4/15/2022 Partial Approval CHRISTOPHER WILSON
Rough-Plumbing 4/15/2022 Partial Approval CHRISTOPHER WILSON
Gas Piping or Gas Test 6/8/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Gas Piping or Gas Test 6/10/2022 Approved GERMAN RODRIGUEZ MENDOZA
Deck 12/19/2023 Approved STEPHANIE SWANSON
Enclosure/Fence 6/13/2024 Approved SEAN HAUPT
Final 8/19/2024 Corrections Issued STEPHANIE SWANSON
Equipment Noise Level 8/20/2024 Approved ANDEY CHAPARRO
Final 8/23/2024 Corrections Issued SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 8/23/2024 SGSOV Approved SEAN HAUPT
Final 9/6/2024 Corrections Issued SEAN HAUPT
Final 9/10/2024 OK to Issue CofO SEAN HAUPT