5131 N STROHM AVE 91601

Certificate Information: 5131 N STROHM AVE 91601

Application / Permit
21047-10000-00352
Plan Check / Job No.
B21LA02868
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
New Swimming Pool & Spa PER CITY STANDARD PLAN # 268
Permit Issued
Issued on 3/26/2021
Issuing Office
Current Status
Issued on 3/26/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/18/2021 APPLICANT
Assigned to Plan Check Engineer 2/18/2021 JOE VO
Corrections Issued 2/18/2021 JOE VO
Applicant returned to address corrections 2/22/2021 CARLOS MONTES
Applicant returned to address corrections 2/24/2021 ZAW HAN
Plan Check Approved 3/24/2021 ZAW HAN
Issued 3/26/2021 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 3/10/2021 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 3/22/2021 GABRIEL ROBLES
Sewer availability Cleared 3/22/2021 GABRIEL ROBLES

Contact Information

Contractor Aqua Pool & Spa Construction Inc; Lic. No.: 1046115-C53 13437 VENTURA BLVD #216      SHERMAN OAKS, CA 91423
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Piping or Gas Test 6/3/2021 No Access for Inspection JENNIFER RABUCHIN
Pre-Gunite 6/3/2021 No Access for Inspection JENNIFER RABUCHIN
Pre-Gunite 6/14/2021 Not Ready for Inspection ARAM AVEDISIAN
Rough-Plumbing 6/14/2021 Partial Approval ARAM AVEDISIAN
Pool Piping 8/6/2021 No Access for Inspection DANIEL DREW
Pre-Gunite 8/6/2021 No Access for Inspection DANIEL DREW
Rough-Electrical 8/6/2021 No Access for Inspection DANIEL DREW
Rough-Plumbing 8/6/2021 No Access for Inspection DANIEL DREW
Pool Piping 8/10/2021 Approved DANIEL DREW
Rough-Electrical 8/10/2021 Approved DANIEL DREW
Rough-Plumbing 8/10/2021 Approved DANIEL DREW
Excavation/Setback/Form/Re-Bar 8/18/2021 No Access for Inspection DANIEL DREW
Final 8/18/2021 No Access for Inspection DANIEL DREW
Pre-Gunite 8/18/2021 No Access for Inspection DANIEL DREW
SGSOV-Seismic Gas S/O Valve 8/18/2021 SGSOV Not Ready DANIEL DREW
Gunite 8/23/2021 Approved DANIEL DREW
Pre-Gunite 8/23/2021 Approved DANIEL DREW
Deputy Shotcrete 8/26/2021 Conditional Approval MICHAEL PELHAM
Deck 3/3/2023 Approved DAVID MATSON
Gas Piping or Gas Test 3/3/2023 Approved DAVID MATSON
Enclosure/Fence 7/12/2024 Approved KEVIN BERBERYAN
Equipment Noise Level 9/18/2024 Approved FELIPE PENICHE
Pool Equipment Noise Test 9/18/2024 Approved FELIPE PENICHE
Final 9/19/2024 Corrections Issued JOSE AVILA
Final 11/8/2024 No Access for Inspection JOSE AVILA
Excavation/Setback/Form/Re-Bar 3/5/2025 No Access for Inspection JOSE AVILA
Final 3/5/2025 No Access for Inspection JOSE AVILA
SGSOV-Seismic Gas S/O Valve 3/5/2025 SGSOV Not Ready JOSE AVILA
Excavation/Setback/Form/Re-Bar 9/18/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 9/18/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 9/18/2025 SGSOV Approved JOSE AVILA