3296 N HUTTON DR 90210
Certificate Information: 3296 N HUTTON DR 90210
- Application / Permit
- 21047-10000-00226
- Plan Check / Job No.
- B21LA01696
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- ePlan swimming pools. NEW 40' X 16' POOL AND SPA PER CITY STANDARD PLAN #265
- Permit Issued
- Issued on 3/20/2021
- Issuing Office
- Current Status
- CofO Issued on 10/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2021 | ARSALAN SHABESTARI |
| Corrections Issued | 2/23/2021 | ARSALAN SHABESTARI |
| Quality Review Completed | 2/25/2021 | HERNAN ARREOLA |
| Plan Check Approved | 3/15/2021 | ARSALAN SHABESTARI |
| Issued | 3/20/2021 | APPLICANT |
| CofO in Progress | 10/13/2022 | GERMAN RODRIGUEZ MENDOZA |
| Permit Finaled | 10/20/2022 | DANIEL ORRANTE |
| CofO Issued | 10/20/2022 | DANIEL ORRANTE |
| Permit Finaled | 10/20/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Miscellaneous | Cleared | 3/2/2021 | TERRI OSBORNE |
| Specific Plan | Cleared | 3/2/2021 | TERRI OSBORNE |
| ZA Case | Cleared | 3/2/2021 | TERRI OSBORNE |
| ZA Case | Cleared | 3/2/2021 | TERRI OSBORNE |
Contact Information
| Contractor | Farahi Construction Inc; Lic. No.: 584288-B | 2933 BEVERLY GLEN CIRCLE LOS ANGELES, CA 90077 |
| Engineer | Zhang,, Yao; Lic. No.: NA74572 | , |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 5/17/2021 | Approved | ANTHONY MCDOWALL |
| Deputy Shotcrete | 6/15/2021 | Conditional Approval | ANTHONY MCDOWALL |
| Grounding or Bonding | 9/13/2021 | Partial Approval | CARLOS MATAMOROS |
| Enclosure/Fence | 3/25/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Enclosure/Fence | 6/21/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Enclosure/Fence | 7/7/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Pool Equipment Noise Test | 7/15/2022 | Not Ready for Inspection | ROBERT CHAVEZ |
| Pool Equipment Noise Test | 7/26/2022 | Approved | ROBERT CHAVEZ |
| ELECTRICAL-Final | 8/18/2022 | Approved | EVAN COOPER |
| Final | 8/18/2022 | Conditional Approval | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 8/18/2022 | SGSOV Approved | EVAN COOPER |
| Final | 10/12/2022 | OK to Issue CofO | GERMAN RODRIGUEZ MENDOZA |