- NEW POOL PER STANDARD PLAN
- Permit Issued
- Issued on 3/24/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/1/2021 | RICARDO RAMIREZ |
| Plan Check Approved | 2/1/2021 | RICARDO RAMIREZ |
| Plan Check Approved | 2/1/2021 | KASANDRA FRONDA |
| Issued | 3/24/2021 | APPLICANT |
| Building Plans Picked Up | 3/26/2021 | APPLICANT |
| CofO in Progress | 8/26/2021 | RICHARD DOCKUS |
| Permit Finaled | 8/29/2022 | DANIEL ORRANTE |
| CofO Issued | 8/29/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/29/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Intex Design And Construction Inc; Lic. No.: 981718-B | 15021 VENTURA BLVD STE 520 SHERMAN OAKS, CA 91403 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/2/2021 | Approved | MICHEL ABAJAN |
| Gas Piping or Gas Test | 6/2/2021 | Approved | MICHEL ABAJAN |
| Grading Pre-Inspection | 6/2/2021 | Partial Inspection | MICHEL ABAJAN |
| Pool Piping | 6/2/2021 | Approved | MICHEL ABAJAN |
| Posting Pre-Inspection | 6/2/2021 | Partial Inspection | MICHEL ABAJAN |
| Pre-Gunite | 6/2/2021 | Approved | MICHEL ABAJAN |
| Pre-Inspection | 6/2/2021 | Partial Inspection | MICHEL ABAJAN |
| Rough-Electrical | 6/2/2021 | Partial Approval | MICHEL ABAJAN |
| Rough-Plumbing | 6/2/2021 | Partial Approval | MICHEL ABAJAN |
| Grounding or Bonding | 7/1/2021 | Approved | ARTHUR SARGSYAN |
| Enclosure/Fence | 8/10/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Pool Equipment Noise Test | 8/24/2021 | Approved | FELIPE PENICHE |
| Final | 8/25/2021 | OK to Issue CofO | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 8/25/2021 | SGSOV Approved | RICHARD DOCKUS |