127 N ST ANDREWS PL 90004
Certificate Information: 127 N ST ANDREWS PL 90004
- Application / Permit
- 21047-10000-00137
- Plan Check / Job No.
- B21LA00978
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 33'4" X 12'0" POOL W/ ATTACHED 6'0" X 6'0" SPA PER STANDARD PLAN 268. 2 OF 2
- Permit Issued
- Issued on 5/20/2021
- Issuing Office
- Current Status
- CofO Issued on 11/29/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/29/2021 | STANLEY RAAP |
| Corrections Issued | 2/2/2021 | STANLEY RAAP |
| Building Plans Picked Up | 2/8/2021 | APPLICANT |
| Applicant returned to address corrections | 3/16/2021 | ZAW HAN |
| Plan Check Approved | 3/18/2021 | ZAW HAN |
| Issued | 5/20/2021 | APPLICANT |
| CofO in Progress | 11/16/2021 | MASHEL JONGERT |
| Permit Finaled | 11/29/2021 | DEROLD HAUFF |
| Permit Finaled | 11/29/2021 | DEROLD HAUFF |
| CofO Issued | 11/29/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/3/2021 | JUAN ASHTON |
| Sewer availability | Cleared | 3/3/2021 | JUAN ASHTON |
Contact Information
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Piping or Gas Test | 6/2/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Grounding or Bonding | 6/2/2021 | Partial Approval | JOSEPH MCGARRY |
| Pool Piping | 6/2/2021 | Partial Approval | JOSEPH MCGARRY |
| Pre-Gunite | 6/2/2021 | Conditional Approval | JOSEPH MCGARRY |
| Rough-Electrical | 6/2/2021 | Partial Approval | JOSEPH MCGARRY |
| Deputy Shotcrete | 6/14/2021 | Conditional Approval | THOMAS LOGRASSO |
| Deck | 8/6/2021 | Approved | ARTHUR SARGSYAN |
| Grounding or Bonding | 8/6/2021 | Approved | ARTHUR SARGSYAN |
| Enclosure/Fence | 9/1/2021 | Approved | ARTHUR SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 10/20/2021 | Approved | ARTHUR SARGSYAN |
| Final | 10/20/2021 | Corrections Issued | ARTHUR SARGSYAN |
| Pre-Gunite | 10/20/2021 | Approved | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 10/20/2021 | SGSOV Approved | ARTHUR SARGSYAN |
| Pool Equipment Noise Test | 10/26/2021 | Approved | ROBERT CHAVEZ |
| Final | 10/28/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 11/15/2021 | Approved | MASHEL JONGERT |
| Final | 11/15/2021 | OK to Issue CofO | MASHEL JONGERT |
| PLUMBING-Final | 11/15/2021 | Approved | MASHEL JONGERT |