871 S TREMAINE AVE 90005

Certificate Information: 871 S TREMAINE AVE 90005

Application / Permit
21047-10000-00130
Plan Check / Job No.
B21LA00874
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
INSTALL NEW POOL/ SPA PER STANDARD PLAN.
Permit Issued
Issued on 4/6/2021
Issuing Office
Current Status
CofO Issued on 9/20/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/21/2021 APPLICANT
Assigned to Plan Check Engineer 1/29/2021 TSE MING HUANG
Corrections Issued 1/30/2021 TSE MING HUANG
Plan Check Approved 3/11/2021 RICARDO RAMIREZ
Issued 4/6/2021 APPLICANT
Building Plans Picked Up 4/8/2021 APPLICANT
CofO in Progress 9/13/2021 CHRIS CHRISTENSEN
Permit Finaled 9/20/2021 DEROLD HAUFF
CofO Issued 9/20/2021 DEROLD HAUFF
Permit Finaled 9/20/2021 DEROLD HAUFF

Permit Application Clearance Information

CPC Cleared 3/1/2021 MINDY NGUYEN

Contact Information

Contractor Owner-Builder       ,
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/15/2021 Approved JOSEPH MCGARRY
Gas Piping or Gas Test 6/15/2021 Not Ready for Inspection JOSEPH MCGARRY
Grounding or Bonding 6/15/2021 Partial Approval JOSEPH MCGARRY
Pool Piping 6/15/2021 Approved JOSEPH MCGARRY
Pre-Gunite 6/15/2021 Approved JOSEPH MCGARRY
Deck 7/22/2021 Approved CHARLES BOGHOSKHAN
Gas Piping or Gas Test 7/22/2021 Not Ready for Inspection CHARLES BOGHOSKHAN
Rough-Electrical 7/22/2021 Not Ready for Inspection CHARLES BOGHOSKHAN
Gas Piping or Gas Test 7/27/2021 Approved ARTHUR SARGSYAN
Rough-Electrical 7/27/2021 Approved ARTHUR SARGSYAN
Pre-Inspection 8/3/2021 Approved ARTHUR SARGSYAN
Enclosure/Fence 8/16/2021 Approved ARTHUR SARGSYAN
Enclosure/Fence 8/17/2021 Approved ARTHUR SARGSYAN
Equipment Noise Level 9/2/2021 Approved RYAN TAGUINES
Final 9/3/2021 Corrections Issued ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 9/3/2021 SGSOV Approved ARTHUR SARGSYAN
Final 9/9/2021 OK to Issue CofO CHRIS CHRISTENSEN