1156 N CORSICA DR 90272
Certificate Information: 1156 N CORSICA DR 90272
- Application / Permit
- 21047-10000-00089
- Plan Check / Job No.
- B21LA00620
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW POOL AND SPA PER STANDARD PLAN #268.
- Permit Issued
- Issued on 2/10/2021
- Issuing Office
- Current Status
- CofO Issued on 4/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 2/10/2021 | FARSHAD ALIMOHAMADI |
| Issued | 2/10/2021 | APPLICANT |
| CofO in Progress | 4/10/2022 | MICHAEL PELHAM |
| Permit Finaled | 4/11/2022 | DANIEL ORRANTE |
| CofO Issued | 4/11/2022 | DANIEL ORRANTE |
| Permit Finaled | 4/11/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZA Case | Cleared | 2/3/2021 | LOUIS ORTEGA |
Contact Information
| Contractor | Williams Craig R Construction Inc; Lic. No.: 479539-B | 9100 WILSHIRE BLVD STE 503E BEVERLY HILLS, CA 90212 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/11/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Grounding or Bonding | 3/11/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Pool Piping | 3/11/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Pre-Gunite | 3/11/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 3/26/2021 | Approved | JOHN KIDWELL |
| Pre-Gunite | 3/26/2021 | Approved | JOHN KIDWELL |
| Grounding or Bonding | 5/14/2021 | Partial Approval | JOHN KIDWELL |
| Grounding or Bonding | 10/28/2021 | Approved | JOHN KIDWELL |
| Enclosure/Fence | 11/15/2021 | Approved | JOHN KIDWELL |
| Final | 1/7/2022 | Corrections Issued | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 1/7/2022 | SGSOV Not Ready | JUAN VALENZUELA |
| Final | 4/10/2022 | Conditional Approval | MICHAEL PELHAM |
| SGSOV-Seismic Gas S/O Valve | 4/10/2022 | SGSOV Approved | MICHAEL PELHAM |