11443 W BOLAS ST 90049
Certificate Information: 11443 W BOLAS ST 90049
- Application / Permit
- 21047-10000-00017
- Plan Check / Job No.
- B21LA00090
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- Eplan. New swimming pool and spa per city of Los Angeles standard plan # 268.
- Permit Issued
- Issued on 6/21/2021
- Issuing Office
- Current Status
- CofO Issued on 6/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2021 | HELEN NGUYEN |
| Corrections Issued | 1/6/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 2/19/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 3/9/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 4/14/2021 | CARLOS MONTES |
| Plan Check Approved | 6/17/2021 | HELEN NGUYEN |
| Issued | 6/21/2021 | APPLICANT |
| CofO in Progress | 5/10/2022 | CARLOS MATAMOROS |
| Permit Finaled | 6/22/2022 | DANIEL ORRANTE |
| CofO Issued | 6/22/2022 | DANIEL ORRANTE |
| Permit Finaled | 6/22/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/6/2021 | HELEN NGUYEN |
| Construction within easement | Cleared | 6/12/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Yd Construction & Development Inc; Lic. No.: 839200-B | 15030 VENTURA BLVD #216 SHERMAN OAKS, CA 91403 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pool Piping | 1/20/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Pre-Gunite | 1/20/2022 | Corrections Issued | CARLOS MATAMOROS |
| Special/Order Compliance | 1/20/2022 | Partial Inspection | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 1/24/2022 | Approved | CARLOS MATAMOROS |
| Gas Piping or Gas Test | 1/24/2022 | Approved | CARLOS MATAMOROS |
| Rough-Plumbing | 1/24/2022 | Approved | CARLOS MATAMOROS |
| Enclosure/Fence | 4/12/2022 | Approved | CARLOS MATAMOROS |
| Pre-Gunite | 4/12/2022 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 4/12/2022 | SGSOV Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 4/28/2022 | Corrections Issued | BRENDAN LOONEY |
| Enclosure/Fence | 4/28/2022 | Approved | BRENDAN LOONEY |
| PLUMBING-Final | 4/28/2022 | Approved | BRENDAN LOONEY |
| Equipment Noise Level | 5/6/2022 | Approved | JAMES VORHIS |
| ELECTRICAL-Final | 5/10/2022 | Approved | CARLOS MATAMOROS |
| Final | 5/10/2022 | OK to Issue CofO | CARLOS MATAMOROS |
| PLUMBING-Final | 5/10/2022 | Approved | CARLOS MATAMOROS |