1056 N MONUMENT ST 90272
Certificate Information: 1056 N MONUMENT ST 90272
- Application / Permit
- 21030-30000-07821
- Plan Check / Job No.
- B21WL05033
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- Grading for (n) garage and retaining wall
- Permit Issued
- Issued on 1/11/2023
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 1/11/2023
Permit Application Status History
| Submitted | 11/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/23/2021 | REZA HAGHIGHAT |
| Corrections Issued | 11/27/2021 | REZA HAGHIGHAT |
| Quality Review Completed | 12/6/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 10/7/2022 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 11/9/2022 | REZA HAGHIGHAT |
| Building Plans Picked Up | 11/10/2022 | APPLICANT |
| Plan Check Approved | 1/10/2023 | REZA HAGHIGHAT |
| Issued | 1/11/2023 | APPLICANT |
Permit Application Clearance Information
| Excavation more than 5-ft deep | Cleared | 9/22/2022 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 1/10/2023 | REZA HAGHIGHAT |
Contact Information
| Contractor | Pacific Coast Design Group Construction Management & Development; Lic. No.: 1003008-B | 16700 BOLLINGER DRIVE PACIFIC PALISADES, CA 90272 |
| Engineer | Ilasin,, John Lacebal; Lic. No.: C67469 | 1011 OARFISH LN OXNARD, CA 93035 |
| Engineer | Samadzadeh,, Hooman Ali; Lic. No.: C87661 | 22430 CRISWELL ST WEST HILLS, CA 91307 |
| Geologist | , ; Lic. No.: GEO2257 | 6634 VALJEAN AVENUE VAN NUYS, CA 91406 |
| Geologist | Van, Meter, James L.; Lic. No.: EG2031 | 6634 VALJEAN AVE VAN NUYS, CA 91406 |
Inspector Information
| RUSSELL BONVOULOIR, (310) 914-3899 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 2/3/2023 | Approved | RUSSELL BONVOULOIR |
| Drainage Devices/Catch Basin | 5/16/2023 | Conditional Approval | VASIL MIHALEV |
| Bottom/Toe | 5/23/2023 | Conditional Approval | RUSSELL BONVOULOIR |
| Rough | 5/23/2023 | Conditional Approval | RUSSELL BONVOULOIR |
| Approved Compaction Report | 8/18/2023 | Not Ready for Inspection | CHARLES POWELL |
| Fill/Backfill | 8/18/2023 | Not Ready for Inspection | CHARLES POWELL |
| Bottom/Toe | 5/28/2024 | Approved | JOHNNY MIRANDA |
| Final | 5/28/2024 | Corrections Issued | JOHNNY MIRANDA |
| Rough | 5/28/2024 | Corrections Issued | JOHNNY MIRANDA |
| Approved Compaction Report | 6/17/2024 | Corrections Issued | MATTHEW JENKINS |
| Final | 9/11/2024 | Partial Inspection | JOHNNY MIRANDA |
| Rough | 9/11/2024 | Partial Inspection | JOHNNY MIRANDA |
| Approved Compaction Report | 9/23/2024 | Approved | MATTHEW JENKINS |