3077 S EARLMAR DR 90064
Certificate Information: 3077 S EARLMAR DR 90064
- Application / Permit
- 21030-30000-07511
- Plan Check / Job No.
- B21WL04889
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- grading for new sfd w/ basement
- Permit Issued
- Issued on 4/29/2022
- Issuing Office
- Current Status
- Permit Finaled on 1/24/2025
Permit Application Status History
| Submitted | 11/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/12/2021 | TARIK SAOUD |
| Corrections Issued | 11/16/2021 | TARIK SAOUD |
| Quality Review Completed | 11/18/2021 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 3/8/2022 | TARIK SAOUD |
| Plan Check Approved | 3/14/2022 | TARIK SAOUD |
| Building Plans Picked Up | 3/24/2022 | APPLICANT |
| Issued | 4/29/2022 | APPLICANT |
| Permit Finaled | 1/23/2025 | VASIL MIHALEV |
Permit Application Clearance Information
| Low Impact Development | Cleared | 1/28/2022 | CHRIS VONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Le,, Thang Huu; Lic. No.: C63174 | 507 MAGELLAN RD ARCADIA, CA 91007 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| JOHNNY MIRANDA, (310) 914-3937 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 5/3/2022 | Approved | AL GAMBLE |
| Deputy Grading | 5/6/2022 | Conditional Approval | AL GAMBLE |
| Bottom/Toe | 5/13/2022 | Corrections Issued | JONATHAN HOM |
| Deputy Grading | 5/16/2022 | Conditional Approval | AL GAMBLE |
| Bottom/Toe | 6/8/2022 | Partial Approval | AL GAMBLE |
| Drainage Devices/Catch Basin | 6/8/2022 | Partial Inspection | AL GAMBLE |
| Deputy Other (see comments) | 7/7/2022 | Partial Approval | AL GAMBLE |
| Deputy Other (see comments) | 7/12/2022 | Approved | AL GAMBLE |
| Sub-Drain | 7/28/2022 | Partial Approval | TIMOTHY POWELL |
| Bottom/Toe | 8/8/2022 | Partial Approval | AL GAMBLE |
| Approved Compaction Report | 11/8/2022 | Partial Approval | CHARLES POWELL |
| Drainage Devices/Catch Basin | 5/2/2024 | Partial Approval | JONATHAN HOM |
| Bottom/Toe | 10/29/2024 | Not Ready for Inspection | MATTHEW JENKINS |
| Final | 10/29/2024 | Corrections Issued | MATTHEW JENKINS |
| Rough | 10/29/2024 | Not Ready for Inspection | MATTHEW JENKINS |
| Bottom/Toe | 11/18/2024 | Partial Inspection | MATTHEW JENKINS |
| Final | 11/18/2024 | Partial Inspection | MATTHEW JENKINS |
| Rough | 11/18/2024 | Partial Inspection | MATTHEW JENKINS |
| Bottom/Toe | 12/4/2024 | Corrections Issued | VASIL MIHALEV |
| Final | 12/4/2024 | Not Ready for Inspection | VASIL MIHALEV |
| Rough | 12/4/2024 | Not Ready for Inspection | VASIL MIHALEV |
| Bottom/Toe | 12/17/2024 | Not Ready for Inspection | VASIL MIHALEV |
| Final | 12/17/2024 | Not Ready for Inspection | VASIL MIHALEV |
| Rough | 12/17/2024 | Not Ready for Inspection | VASIL MIHALEV |
| Bottom/Toe | 1/23/2025 | Approved | VASIL MIHALEV |
| Final | 1/23/2025 | Permit Finaled | VASIL MIHALEV |
| Rough | 1/23/2025 | Approved | VASIL MIHALEV |