23445 W BALMORAL LANE 91307

Certificate Information: 23445 W BALMORAL LANE 91307

Application / Permit
21030-30000-06694
Plan Check / Job No.
B21WL04392
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
Site grading for new ADU, new ALQ, and retaining wall
Permit Issued
Issued on 12/6/2022
Issuing Office
Current Status
Permit Finaled on 9/18/2025

Permit Application Status History

Submitted 10/5/2021 APPLICANT
Assigned to Plan Check Engineer 10/14/2021 REZA HAGHIGHAT
Corrections Issued 10/17/2021 REZA HAGHIGHAT
Quality Review Completed 10/27/2021 TARIK SAOUD
Applicant returned to address corrections 5/19/2022 REZA HAGHIGHAT
Applicant returned to address corrections 8/26/2022 REZA HAGHIGHAT
Plan Check Approved 9/1/2022 REZA HAGHIGHAT
Issued 12/6/2022 APPLICANT
Building Plans Picked Up 1/12/2023 APPLICANT
Permit Finaled 9/17/2025 MANUEL TEJADA

Permit Application Clearance Information

CPC Cleared 1/11/2022 KENTON TRINH
Grading Pre-Inspection Cleared 1/13/2022 VASIL MIHALEV
Excavation more than 5-ft deep Cleared 9/1/2022 CALOSHA APPROVED

Contact Information

Contractor Bardi Edmund; Lic. No.: 1037330-B P O BOX 4011      WEST HILLS, CA 91308
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316
Engineer Cai,, Luo B; Lic. No.: C80352 9428 ETAON AVE M      CHATSWORTH, CA 91311
Geologist Tsao,, Tze-Tzong; Lic. No.: EG1783 9428 ETON AVENUE #M      CHATSWORTH, CA 91311

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation 12/9/2022 Not Ready for Inspection ALEXANDER HELFER
Initial Grading 12/9/2022 Approved ALEXANDER HELFER
Excavation 3/3/2023 Approved ROBERT PINA
Initial Grading 3/3/2023 Partial Approval ROBERT PINA
Deputy Other (see comments) 3/31/2023 No Access for Inspection MICHAEL TEMPLE
Sub-Drain 4/10/2023 Order to Comply Issued ROBERT PINA
Fill/Backfill 5/5/2023 Not Ready for Inspection BRIAN MILLER
Sub-Drain 11/8/2023 No Access for Inspection GERMAN RODRIGUEZ MENDOZA
Fill/Backfill 11/27/2023 Corrections Issued BRIAN MILLER
Sub-Drain 11/27/2023 Corrections Issued BRIAN MILLER
Sub-Drain 8/8/2024 Partial Approval GERMAN RODRIGUEZ MENDOZA
Sub-Drain 9/5/2024 Partial Approval GERMAN RODRIGUEZ MENDOZA
Approved Compaction Report 12/6/2024 Approved ROBERT PINA
Bottom/Toe 9/17/2025 Approved MANUEL TEJADA
Final 9/17/2025 Permit Finaled MANUEL TEJADA
Rough 9/17/2025 Approved MANUEL TEJADA