1018 S HILGARD AVE 90024

Certificate Information: 1018 S HILGARD AVE 90024

Application / Permit
21030-30000-06277
Plan Check / Job No.
B21WL04172
Group
Building
Type
Grading
Sub-Type
Commercial
Primary Use
(70) Grading - Hillside
Work Description
Site grading for new retaining wall and ADA ramp (51 CY)
Permit Issued
Issued on 9/13/2022
Issuing Office
Current Status
Permit Finaled on 1/30/2025

Permit Application Status History

Submitted 9/19/2021 APPLICANT
Assigned to Plan Check Engineer 10/14/2021 REZA HAGHIGHAT
Corrections Issued 10/16/2021 REZA HAGHIGHAT
Quality Review Completed 10/27/2021 TARIK SAOUD
Disabled Access Plans Picked Up 12/9/2021 APPLICANT
Plan Check Approved 8/16/2022 REZA HAGHIGHAT
Building Plans Picked Up 8/24/2022 APPLICANT
Issued 9/13/2022 APPLICANT
Permit Finaled 1/30/2025 ALEXANDER HELFER

Permit Application Clearance Information

"Q" conditions Cleared 8/17/2022 ANACANY HURTADO
ZA Case Cleared 8/17/2022 ANACANY HURTADO
ZA Case Cleared 8/17/2022 ANACANY HURTADO
Specific Plan Cleared 8/22/2022 KEVIN FULTON
Grading Pre-Inspection Cleared 8/23/2022 REZA HAGHIGHAT

Contact Information

Architect Bonneau,, Kirstyn I; Lic. No.: C36535 234 E. COLORADO BLVD STE. 700      PASADENA, CA 91101
Contractor Del Amo Construction Inc; Lic. No.: 744458-B 23840 MADISON STREET      TORRANCE, CA 90505
Engineer Kelly,, John Roland; Lic. No.: C36693 865 RIDGESIDE DR      MONROVIA, CA 91016
Engineer Schulz,, Les Eric; Lic. No.: S2570 346 N LIMA      SIERRA MADRE, CA 91024
Geologist , ; Lic. No.: GEO3092 26632 EL TOBOSO      MISSION VIEJO, C 92691

Inspector Information

JOHNNY MIRANDA, (310) 914-3937 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Bottom/Toe 5/15/2023 Partial Inspection MATTHEW JENKINS
Final 5/15/2023 Partial Inspection MATTHEW JENKINS
Rough 5/15/2023 Partial Inspection MATTHEW JENKINS
Drainage Devices/Catch Basin 6/5/2023 Partial Approval MATTHEW JENKINS
Drainage Devices/Catch Basin 6/27/2023 Partial Inspection RUSSELL BONVOULOIR
Final 1/22/2025 Corrections Issued VASIL MIHALEV
Rough 1/22/2025 Approved VASIL MIHALEV
Approved Compaction Report 1/30/2025 Approved ALEXANDER HELFER
Final 1/30/2025 Permit Finaled ALEXANDER HELFER