636 N WALTHER WAY 90049

Certificate Information: 636 N WALTHER WAY 90049

Application / Permit
21030-30000-06087
Plan Check / Job No.
B21WL04038
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
grading for new pool & pool house.
Permit Issued
Issued on 10/25/2022
Issuing Office
Current Status
Permit Finaled on 2/27/2025

Permit Application Status History

Submitted 9/10/2021 APPLICANT
Assigned to Plan Check Engineer 9/30/2021 FELIPE HERNANDEZ
Corrections Issued 10/6/2021 FELIPE HERNANDEZ
Quality Review Completed 10/18/2021 TARIK SAOUD
Applicant returned to address corrections 7/6/2022 FELIPE HERNANDEZ
Applicant returned to address corrections 8/10/2022 FELIPE HERNANDEZ
Applicant returned to address corrections 8/16/2022 FELIPE HERNANDEZ
Applicant returned to address corrections 9/6/2022 CHIHARU SUZUKI
Plan Check Approved 10/17/2022 CHIHARU SUZUKI
Issued 10/25/2022 APPLICANT
Building Plans Picked Up 10/26/2022 APPLICANT
Permit Finaled 2/26/2025 JOHNNY MIRANDA

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/9/2022 JENSON LEE
Miscellaneous Cleared 5/9/2022 SAUL GARCIA
Excavation more than 5-ft deep Cleared 8/10/2022 CALOSHA APPROVED
GPI Written Notices Cleared 8/10/2022 FELIPE HERNANDEZ
Grading Pre-Inspection Cleared 8/10/2022 FELIPE HERNANDEZ

Contact Information

Architect Schoeplein,, Marc; Lic. No.: C24842 960 BLUEGRASS WAY      LOS ANGELES, CA 90049
Contractor Basix Designs & Remodeling Inc; Lic. No.: 769443-B 650 S HIGHLAND AVE      LOS ANGELES, CA 90036
Engineer Garza,, Omar Leonel; Lic. No.: S5593 600 WILSHIRE BLVD 760      LOS ANGELES, CA 90017
Engineer Mahn,, Jonathan Edward; Lic. No.: C60293 12848 FOOTHILL BLVD      SYLMAR, CA 91381
Geologist Triebold,, Mark John; Lic. No.: EG1796 6906 QUITO COURT      CAMARILLO, CA 93012

Inspector Information

GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sub-Drain 6/20/2023 Partial Approval CHARLES POWELL
Bottom/Toe 9/20/2023 Partial Approval CHARLES POWELL
Sub-Drain 10/5/2023 Partial Approval CHARLES POWELL
Sub-Drain 11/14/2023 Partial Approval CHARLES POWELL
Approved Compaction Report 5/17/2024 Corrections Issued MATTHEW JENKINS
Rough 5/17/2024 Corrections Issued MATTHEW JENKINS
Bottom/Toe 6/24/2024 Not Ready for Inspection AL GAMBLE
Final 6/24/2024 Not Ready for Inspection AL GAMBLE
Rough 6/24/2024 Not Ready for Inspection AL GAMBLE
Bottom/Toe 6/27/2024 Partial Inspection JOHNNY MIRANDA
Final 6/27/2024 Partial Inspection JOHNNY MIRANDA
Rough 6/27/2024 Partial Inspection JOHNNY MIRANDA
Rough 9/9/2024 Corrections Issued MATTHEW JENKINS
Bottom/Toe 2/26/2025 Approved JOHNNY MIRANDA
Final 2/26/2025 Permit Finaled JOHNNY MIRANDA
Rough 2/26/2025 Approved JOHNNY MIRANDA