1204 N CHICKORY LANE 90049
Certificate Information: 1204 N CHICKORY LANE 90049
- Application / Permit
- 21030-30000-06026
- Plan Check / Job No.
- B21WL03940
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- SITE GRADING FOR NEW SFD OVER 1-LEVEL BASEMENT AND RET. WALLS
- Permit Issued
- Issued on 8/31/2022
- Issuing Office
- Current Status
- Permit Finaled on 7/18/2025
Permit Application Status History
| Submitted | 9/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2021 | REZA HAGHIGHAT |
| Corrections Issued | 10/2/2021 | REZA HAGHIGHAT |
| Quality Review Completed | 10/18/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 4/18/2022 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 4/29/2022 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 5/12/2022 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 8/26/2022 | REZA HAGHIGHAT |
| Plan Check Approved | 8/29/2022 | REZA HAGHIGHAT |
| Issued | 8/31/2022 | APPLICANT |
| Building Plans Picked Up | 9/1/2022 | APPLICANT |
| Permit Finaled | 7/15/2025 | JOHNNY MIRANDA |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/12/2022 | REZA HAGHIGHAT |
Contact Information
| Contractor | J A L Inc; Lic. No.: 986943-B | 8721 W SUNSET BLVD STE 208 WEST HOLLYWOOD, CA 90069 |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Geologist | , ; Lic. No.: GEO2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 9/2/2022 | Approved | TIMOTHY POWELL |
| Excavation | 9/7/2022 | Partial Inspection | TIMOTHY POWELL |
| Deputy Other (see comments) | 9/22/2022 | Partial Approval | CHARLES POWELL |
| Excavation | 9/23/2022 | Partial Approval | CHARLES POWELL |
| Excavation | 9/27/2022 | Approved | CHARLES POWELL |
| Bottom/Toe | 10/11/2022 | Partial Approval | KIRK LINKLATER |
| Deputy Grading | 10/11/2022 | Partial Approval | CHARLES POWELL |
| Deputy Other (see comments) | 10/21/2022 | Partial Approval | CHARLES POWELL |
| Excavation | 10/21/2022 | Partial Approval | CHARLES POWELL |
| Bottom/Toe | 11/18/2022 | Partial Approval | CHARLES POWELL |
| Private Sewage Disposal System | 11/18/2022 | Partial Approval | CHARLES POWELL |
| Private Sewage Disposal System | 12/2/2022 | Partial Approval | CHARLES POWELL |
| Sub-Drain | 12/15/2022 | Conditional Approval | JONATHAN HOM |
| Sub-Drain | 1/12/2023 | Partial Approval | MATTHEW JENKINS |
| Sub-Drain | 1/23/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Excavation | 1/31/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Sub-Drain | 3/16/2023 | Partial Approval | CHARLES POWELL |
| Sub-Drain | 3/24/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Sub-Drain | 4/11/2023 | Partial Approval | CHARLES POWELL |
| Sub-Drain | 4/14/2023 | Partial Approval | CHARLES POWELL |
| Sub-Drain | 4/28/2023 | Partial Approval | CHARLES POWELL |
| Sub-Drain | 5/2/2023 | Partial Approval | CHARLES POWELL |
| Sub-Drain | 7/10/2023 | Partial Approval | CHARLES POWELL |
| Deputy Other (see comments) | 7/27/2023 | Partial Approval | CHARLES POWELL |
| Excavation | 7/27/2023 | Not Ready for Inspection | VASIL MIHALEV |
| Bottom/Toe | 9/28/2023 | Partial Inspection | JOHNNY MIRANDA |
| Private Sewage Disposal System | 9/28/2023 | Partial Inspection | JOHNNY MIRANDA |
| Private Sewage Disposal System | 10/23/2023 | Partial Approval | CHARLES POWELL |
| Approved Compaction Report | 5/7/2025 | Corrections Issued | MATTHEW JENKINS |
| Approved Compaction Report | 6/12/2025 | Approved | MATTHEW JENKINS |
| Bottom/Toe | 7/15/2025 | Approved | JOHNNY MIRANDA |
| Final | 7/15/2025 | Permit Finaled | JOHNNY MIRANDA |
| Rough | 7/15/2025 | Approved | JOHNNY MIRANDA |