991 S WELLESLEY AVE 90049

Certificate Information: 991 S WELLESLEY AVE 90049

Application / Permit
21030-30000-02981
Plan Check / Job No.
B21WL01926
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(60) Grading - Non-Hillside
Work Description
Grading for (N) retaining wall / pool
Permit Issued
Issued on 10/18/2021
Issuing Office
Current Status
Permit Finaled on 7/6/2022

Permit Application Status History

Submitted 5/10/2021 APPLICANT
Assigned to Plan Check Engineer 5/26/2021 HOOMAN HAJIZADEH
Corrections Issued 6/11/2021 HOOMAN HAJIZADEH
Quality Review Completed 6/21/2021 TARIK SAOUD
Applicant returned to address corrections 10/7/2021 HOOMAN HAJIZADEH
Plan Check Approved 10/8/2021 HOOMAN HAJIZADEH
Issued 10/18/2021 APPLICANT
Permit Finaled 7/5/2022 CHARLES POWELL

Permit Application Clearance Information

Watercourse Cleared 8/19/2021 MAHELET GEBEYHU
Eng Process Fee Ord 176,300 Cleared 8/20/2021 MAHELET GEBEYHU

Contact Information

Contractor Decardo'S Pools And Landscape Inc; Lic. No.: 532429-C27 23705 VANOWEN ST #114      WEST HILLS, CA 91307
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807
Engineer Markov,, George P; Lic. No.: C55855 1623 THOMPSON AVE      GLENDALE, CA 91201

Inspector Information

GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation 11/9/2021 Partial Approval CHARLES POWELL
FLOOD-Proofing Certificate 11/9/2021 Not Ready for Inspection CHARLES POWELL
Initial Grading 11/9/2021 Partial Approval CHARLES POWELL
Rough 11/9/2021 Partial Approval CHARLES POWELL
Bottom/Toe 1/5/2022 Corrections Issued CHARLES POWELL
Excavation 1/5/2022 Corrections Issued CHARLES POWELL
Bottom/Toe 1/11/2022 Approved CHARLES POWELL
Excavation 1/11/2022 Partial Approval CHARLES POWELL
Fill/Backfill 1/11/2022 Approved CHARLES POWELL
FLOOD-Proofing Certificate 6/9/2022 Approved CHARLES POWELL
Final 6/9/2022 Corrections Issued CHARLES POWELL
Rough 6/9/2022 Approved CHARLES POWELL
Approved Compaction Report 6/24/2022 Partial Approval CHARLES POWELL
Final 7/5/2022 Permit Finaled CHARLES POWELL