13047 W ROSE AVE 90066
Certificate Information: 13047 W ROSE AVE 90066
- Application / Permit
- 21030-30000-01984
- Plan Check / Job No.
- B21WL01301
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- Grading for addition to main house, new ADU, pool & spa , and retaining walls
- Permit Issued
- Issued on 2/15/2022
- Issuing Office
- Current Status
- Permit Finaled on 6/19/2025
Permit Application Status History
| Submitted | 3/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2021 | FELIPE HERNANDEZ |
| Corrections Issued | 4/8/2021 | FELIPE HERNANDEZ |
| Quality Review Completed | 4/16/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 9/9/2021 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 11/30/2021 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 12/22/2021 | FELIPE HERNANDEZ |
| Plan Check Approved | 1/12/2022 | FELIPE HERNANDEZ |
| Issued | 2/15/2022 | APPLICANT |
| Building Plans Picked Up | 2/25/2022 | APPLICANT |
| Permit Finaled | 6/18/2025 | LANNY MERRICK |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/21/2021 | HISASHI KOBAYAKAWA |
| Work Adjacent to Public Way | Cleared | 10/14/2021 | SAUL GARCIA |
| GPI Written Notices | Cleared | 1/11/2022 | FELIPE HERNANDEZ |
| Grading Pre-Inspection | Cleared | 1/11/2022 | FELIPE HERNANDEZ |
Contact Information
| Contractor | Stanfield Barney Construction; Lic. No.: 401178-B | 5223 BASCULE AVE WOODLAND HILLS, CA 91364 |
| Engineer | Messiha,, Hany Gamil; Lic. No.: C56766 | 19648 MULBERRY DR WALNUT, CA 91789 |
| Engineer | Miscione,, Frank Vincent; Lic. No.: C69031 | 30014 LEXINGTON VAL VERDE, CA 91384 |
| Geologist | Schick,, John Wayne; Lic. No.: EG1300 | 7650 HASKELL AVENUE STE D VAN NUYS, CA 91406 |
Inspector Information
| JOHNNY MIRANDA, (310) 914-3937 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 6/24/2022 | Approved | AL GAMBLE |
| Sub-Drain | 8/29/2022 | Approved | CHARLES POWELL |
| Sub-Drain | 8/30/2022 | Partial Inspection | JONATHAN HOM |
| Bottom/Toe | 9/19/2022 | Not Ready for Inspection | AL GAMBLE |
| Rough | 9/19/2022 | Not Ready for Inspection | AL GAMBLE |
| Drainage Devices/Catch Basin | 9/18/2023 | Corrections Issued | MATTHEW JENKINS |
| Drainage Devices/Catch Basin | 9/20/2023 | Partial Approval | MATTHEW JENKINS |
| Excavation | 8/7/2024 | Not Ready for Inspection | MATTHEW JENKINS |
| Sub-Drain | 9/24/2024 | Partial Approval | MATTHEW JENKINS |
| Approved Compaction Report | 5/9/2025 | Corrections Issued | MATTHEW JENKINS |
| Bottom/Toe | 5/28/2025 | Not Ready for Inspection | AL GAMBLE |
| Final | 5/28/2025 | Not Ready for Inspection | LANNY MERRICK |
| Rough | 5/28/2025 | Not Ready for Inspection | AL GAMBLE |
| Bottom/Toe | 6/18/2025 | Approved | LANNY MERRICK |
| Final | 6/18/2025 | Permit Finaled | LANNY MERRICK |