2707 S CLUB DR 90064
Certificate Information: 2707 S CLUB DR 90064
- Application / Permit
- 21030-30000-00284
- Plan Check / Job No.
- B21WL00198
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- Grading for new SFD with basement and retaining walls.
- Permit Issued
- Issued on 8/9/2021
- Issuing Office
- Current Status
- Permit Finaled on 7/13/2023
Permit Application Status History
| Submitted | 1/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/28/2021 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 2/1/2021 | KAMRAN GHOTBI RAVANDI |
| Quality Review Completed | 2/3/2021 | CHIHARU SUZUKI |
| Building Plans Picked Up | 2/4/2021 | APPLICANT |
| Applicant returned to address corrections | 6/4/2021 | SERGIO SILVA |
| Plan Check Approved | 6/24/2021 | SERGIO SILVA |
| Issued | 8/9/2021 | APPLICANT |
| Permit Finaled | 7/12/2023 | MATTHEW JENKINS |
Permit Application Clearance Information
| Excavation more than 5-ft deep | Cleared | 6/4/2021 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 6/4/2021 | KAMRAN GHOTBI RAVANDI |
Contact Information
| Contractor | Inhance Construction Inc; Lic. No.: 1073871-B | 7257 BEVERLY RD STE 205 LOS ANGELES, CA 90036 |
| Engineer | Foroughi,, Mohammad Hossein; Lic. No.: C66179 | 767 NORTH HILL STREET 407 LOS ANGELES, CA 90012 |
| Engineer | Messiha,, Hany Gamil; Lic. No.: C56766 | 19648 MULBERRY DR WALNUT, CA 91789 |
Inspector Information
| JOHNNY MIRANDA, (310) 914-3937 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sub-Drain | 10/4/2021 | Conditional Approval | LANNY MERRICK |
| Sub-Drain | 1/20/2022 | Partial Approval | AL GAMBLE |
| Sub-Drain | 3/9/2022 | Not Ready for Inspection | AL GAMBLE |
| Approved Compaction Report | 6/20/2023 | Partial Inspection | MATTHEW JENKINS |
| Bottom/Toe | 6/20/2023 | Partial Inspection | MATTHEW JENKINS |
| Final | 6/20/2023 | Corrections Issued | MATTHEW JENKINS |
| Rough | 6/20/2023 | Partial Inspection | MATTHEW JENKINS |
| Bottom/Toe | 6/26/2023 | Partial Inspection | MATTHEW JENKINS |
| Drainage Devices/Catch Basin | 6/26/2023 | Partial Approval | MATTHEW JENKINS |
| Final | 6/26/2023 | Not Ready for Inspection | MATTHEW JENKINS |
| Rough | 6/26/2023 | Partial Inspection | MATTHEW JENKINS |
| Final | 6/28/2023 | Partial Inspection | MATTHEW JENKINS |
| Approved Compaction Report | 6/29/2023 | Approved | MATTHEW JENKINS |
| Bottom/Toe | 6/29/2023 | Corrections Issued | MATTHEW JENKINS |
| Rough | 6/29/2023 | Partial Inspection | MATTHEW JENKINS |
| Final | 7/5/2023 | Partial Inspection | MATTHEW JENKINS |
| Bottom/Toe | 7/12/2023 | Approved | MATTHEW JENKINS |
| Final | 7/12/2023 | Permit Finaled | MATTHEW JENKINS |
| Rough | 7/12/2023 | Approved | MATTHEW JENKINS |