11052 N INDEPENDENCE AVE 91311

Certificate Information: 11052 N INDEPENDENCE AVE 91311

Application / Permit
21030-20000-07105
Plan Check / Job No.
B21VN14407
Group
Building
Type
Grading
Sub-Type
Commercial
Primary Use
(70) Grading - Hillside
Work Description
SITE PREPARATION
Permit Issued
Issued on 5/31/2022
Issuing Office
Valley
Current Status
Permit Finaled on 10/24/2023

Permit Application Status History

Submitted 10/25/2021 APPLICANT
Assigned to Plan Check Engineer 11/4/2021 RARES BODEA
Disabled Access Plans Picked Up 11/9/2021 APPLICANT
Green Plans Picked Up 11/9/2021 APPLICANT
Corrections Issued 11/12/2021 RARES BODEA
Quality Review Completed 11/18/2021 STEVEN KIM
Building Plans Picked Up 11/23/2021 APPLICANT
Applicant returned to address corrections 2/8/2022 RARES BODEA
Applicant returned to address corrections 5/27/2022 RARES BODEA
Plan Check Approved 5/31/2022 RARES BODEA
Issued 5/31/2022 APPLICANT
Permit Finaled 10/23/2023 GERMAN RODRIGUEZ MENDOZA

Permit Application Clearance Information

Miscellaneous Cleared 4/20/2022 LAUREN PADICK
Tract Map conditions Cleared 4/20/2022 LAUREN PADICK
Tract Map conditions Cleared 4/20/2022 LAUREN PADICK
Tract Map conditions Cleared 4/20/2022 LAUREN PADICK
ZA Case Cleared 4/20/2022 LAUREN PADICK
Low Impact Development Cleared 5/13/2022 ORVAL HERNANDEZ-MARCI
CPC Cleared 5/18/2022 MIGUEL GAMBOA
Grading Pre-Inspection Cleared 5/31/2022 RARES BODEA

Contact Information

Contractor Del Amo Construction Inc; Lic. No.: 744458-B 23840 MADISON STREET      TORRANCE, CA 90505
Engineer Davis,, Richard Hays; Lic. No.: C48082 2015 CANTATA DR      LOS ANGELES, CA 90068

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Bottom/Toe 6/2/2022 Partial Approval BRIAN MILLER
Bottom/Toe 6/7/2022 Partial Approval BRIAN MILLER
Deputy Grading 6/7/2022 Approved BRIAN MILLER
Deputy Grading 6/8/2022 Approved BRIAN MILLER
Deputy Grading 6/9/2022 Approved VASIL MIHALEV
Bottom/Toe 6/10/2022 Partial Approval BRIAN MILLER
Deputy Grading 6/10/2022 Approved BRIAN MILLER
Fill/Backfill 6/10/2022 Partial Approval BRIAN MILLER
Rough 6/10/2022 Approved BRIAN MILLER
Bottom/Toe 6/16/2022 Partial Approval BRIAN MILLER
Bottom/Toe 6/23/2022 Partial Approval BRIAN MILLER
Approved Compaction Report 6/28/2022 Partial Inspection BRIAN MILLER
Bottom/Toe 6/28/2022 Partial Approval BRIAN MILLER
Approved Compaction Report 6/30/2022 Approved BRIAN MILLER
Approved Compaction Report 7/6/2022 Approved VASIL MIHALEV
Drainage Devices/Catch Basin 6/9/2023 Partial Approval BRIAN MILLER
Drainage Devices/Catch Basin 7/6/2023 Partial Approval BRIAN MILLER
Drainage Devices/Catch Basin 7/17/2023 Partial Approval BRIAN MILLER
Sub-Drain 7/17/2023 Partial Approval BRIAN MILLER
Drainage Devices/Catch Basin 7/21/2023 Partial Approval ROBERT PINA
Sub-Drain 7/21/2023 Partial Approval ROBERT PINA
Bottom/Toe 10/2/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Final 10/2/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Approved Compaction Report 10/12/2023 Approved MANUEL TEJADA
Bottom/Toe 10/16/2023 Approved GERMAN RODRIGUEZ MENDOZA
Final 10/16/2023 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Final 10/23/2023 Permit Finaled GERMAN RODRIGUEZ MENDOZA