9219 W SAWYER ST 90035

Certificate Information: 9219 W SAWYER ST 90035

Application / Permit
21030-20000-06662
Plan Check / Job No.
B21VN13475
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
EXCAVATION AND BACKFILL FOR BASEMENT UNDER 21014-20000-05008 AND SITE PREP ALL WORK PER ENGINEERING
Permit Issued
Issued on 6/6/2022
Issuing Office
Valley
Current Status
Permit Finaled on 5/29/2024

Permit Application Status History

Submitted 10/5/2021 APPLICANT
Assigned to Plan Check Engineer 10/28/2021 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 11/12/2021 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 11/19/2021 OMID HEDAYAT
Building Plans Picked Up 11/22/2021 APPLICANT
Applicant returned to address corrections 12/13/2021 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 2/14/2022 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 2/16/2022 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 4/5/2022 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 5/13/2022 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 6/6/2022 JON BLAINE
Issued 6/6/2022 APPLICANT
Permit Finaled 5/28/2024 VASIL MIHALEV

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/6/2022 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 2/14/2022 HISASHI KOBAYAKAWA
Excavation more than 5-ft deep Cleared 2/28/2022 CALOSHA APPROVED
Grading Pre-Inspection Cleared 5/13/2022 SEWADA ZADOORAN MILAGARDI

Contact Information

Contractor Inhance Construction Inc; Lic. No.: 1073871-B 7257 BEVERLY RD STE 205      LOS ANGELES, CA 90036

Inspector Information

JOHNNY MIRANDA, (310) 914-3937 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 8/22/2022 Approved AL GAMBLE
Deputy Grading 8/30/2022 Partial Approval AL GAMBLE
Deputy Grading 9/1/2022 Approved AL GAMBLE
Sub-Drain 2/10/2023 Partial Inspection MATTHEW JENKINS
Approved Compaction Report 8/16/2023 Corrections Issued MATTHEW JENKINS
Approved Compaction Report 9/25/2023 Approved MATTHEW JENKINS
Drainage Devices/Catch Basin 4/12/2024 Partial Inspection MATTHEW JENKINS
Bottom/Toe 5/15/2024 Approved RUSSELL BONVOULOIR
Final 5/15/2024 Not Ready for Inspection RUSSELL BONVOULOIR
Rough 5/15/2024 Approved RUSSELL BONVOULOIR
Drainage Devices/Catch Basin 5/28/2024 Approved VASIL MIHALEV
Final 5/28/2024 Permit Finaled VASIL MIHALEV