4835 N LANKERSHIM BLVD 91601
Certificate Information: 4835 N LANKERSHIM BLVD 91601
- Application / Permit
- 21030-20000-06088
- Plan Check / Job No.
- B21VN03373
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- GRADING WORK FOR (N) RESTAURANT
- Permit Issued
- Issued on 2/15/2023
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 6/27/2024
Permit Application Status History
| Submitted | 3/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2021 | CHON CHIO KUO |
| Corrections Issued | 5/20/2021 | CHON CHIO KUO |
| Quality Review Completed | 5/20/2021 | STEVEN KIM |
| Applicant returned to address corrections | 7/20/2021 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 8/5/2021 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 8/6/2021 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 9/10/2021 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 10/12/2021 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 4/1/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 4/28/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 9/30/2022 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 12/15/2022 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 1/19/2023 | MARVEL DELACRUZ |
| Plan Check Approved | 1/26/2023 | MARVEL DELACRUZ |
| Issued | 2/15/2023 | APPLICANT |
| Permit Finaled | 6/26/2024 | MANUEL TEJADA |
Permit Application Clearance Information
| Work Adjacent to Public Way | Cleared | 10/17/2022 | DAGOVERTO GUERRERO |
| Encroachment in public way | Cleared | 10/18/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 10/18/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Parkway C & A Lp; Lic. No.: 1023585-B | 1000 CIVIC CIRCLE LEWISVILLE, TX 75067 |
Inspector Information
| MATTHEW JENKINS, (818) 374-4357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 3/20/2023 | Approved | BRIAN MILLER |
| Initial Grading | 3/20/2023 | Approved | BRIAN MILLER |
| Deputy Grading | 3/24/2023 | Approved | ROBERT PINA |
| Deputy Grading | 3/28/2023 | Approved | MANUEL TEJADA |
| Drainage Devices/Catch Basin | 4/19/2023 | Approved | ROBERT PINA |
| Bottom/Toe | 4/21/2023 | Partial Approval | ROBERT PINA |
| Drainage Devices/Catch Basin | 4/24/2023 | Partial Approval | MANUEL TEJADA |
| Approved Compaction Report | 5/23/2023 | Corrections Issued | BRIAN MILLER |
| Approved Compaction Report | 6/2/2023 | Approved | BRIAN MILLER |
| Drainage Devices/Catch Basin | 11/6/2023 | Partial Approval | MANUEL TEJADA |
| Irrigation/Landscape | 11/9/2023 | Partial Inspection | MANUEL TEJADA |
| Drainage Devices/Catch Basin | 12/4/2023 | No Access for Inspection | MANUEL TEJADA |
| Irrigation/Landscape | 12/4/2023 | No Access for Inspection | MANUEL TEJADA |
| Irrigation/Landscape | 12/7/2023 | Partial Inspection | MANUEL TEJADA |
| Bottom/Toe | 6/26/2024 | Approved | MANUEL TEJADA |
| Final | 6/26/2024 | Permit Finaled | MANUEL TEJADA |
| Rough | 6/26/2024 | Approved | MANUEL TEJADA |