675 N MUSKINGUM AVE 90272
Certificate Information: 675 N MUSKINGUM AVE 90272
- Application / Permit
- 21030-20000-05055
- Plan Check / Job No.
- B21VN10062
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- EXCAVATION AND BACKFILL FOR SFD AND RETAINING WALLS - 652 CY
- Permit Issued
- Issued on 9/7/2022
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 6/25/2024
Permit Application Status History
| Submitted | 8/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2021 | MOHAMMAD ESMAILI |
| Corrections Issued | 9/10/2021 | MOHAMMAD ESMAILI |
| Quality Review Completed | 9/10/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 9/14/2021 | APPLICANT |
| Applicant returned to address corrections | 5/28/2022 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 8/10/2022 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 8/15/2022 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 8/17/2022 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 8/19/2022 | MOHAMMAD ESMAILI |
| Plan Check Approved | 8/25/2022 | MOHAMMAD ESMAILI |
| Issued | 9/7/2022 | APPLICANT |
| Permit Finaled | 6/25/2024 | JOHNNY MIRANDA |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/10/2021 | DINAH GARIN |
| GPI Written Notices | Cleared | 2/7/2022 | MOHAMMAD ESMAILI |
| Grading Pre-Inspection | Cleared | 2/7/2022 | MOHAMMAD ESMAILI |
| Roof/Waste drainage to street | Cleared | 5/5/2022 | DINAH GARIN |
| Excavation more than 5-ft deep | Cleared | 8/25/2022 | CALOSHA APPROVED |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 8887 W FALMINGO RD STE 101 LAS VEGAS, NV 89147 |
Inspector Information
| RAMAZANALI ALMASI, (310) 914-3899 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 9/20/2022 | Approved | TIMOTHY POWELL |
| Drainage Devices/Catch Basin | 10/20/2022 | Not Ready for Inspection | TIMOTHY POWELL |
| Sub-Drain | 10/20/2022 | Not Ready for Inspection | TIMOTHY POWELL |
| Drainage Devices/Catch Basin | 10/26/2022 | Partial Inspection | TIMOTHY POWELL |
| Sub-Drain | 10/26/2022 | Partial Inspection | TIMOTHY POWELL |
| Excavation | 12/6/2022 | Partial Approval | JONATHAN HOM |
| Fill/Backfill | 2/21/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Sub-Drain | 2/21/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Approved Compaction Report | 4/26/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Sub-Drain | 6/14/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Bottom/Toe | 4/2/2024 | Approved | JOHNNY MIRANDA |
| Final | 4/2/2024 | Corrections Issued | JOHNNY MIRANDA |
| Rough | 4/2/2024 | Approved | JOHNNY MIRANDA |
| Approved Compaction Report | 4/19/2024 | Approved | MATTHEW JENKINS |
| Final | 4/25/2024 | Not Ready for Inspection | JOHNNY MIRANDA |
| Approved Compaction Report | 5/16/2024 | Approved | MATTHEW JENKINS |
| Final | 6/11/2024 | Not Ready for Inspection | AL GAMBLE |
| Final | 6/25/2024 | Permit Finaled | JOHNNY MIRANDA |