14201 W NORDHOFF ST 91402

Certificate Information: 14201 W NORDHOFF ST 91402

Application / Permit
21030-20000-04875
Plan Check / Job No.
B21VN09643
Group
Building
Type
Grading
Sub-Type
Apartment
Primary Use
(60) Grading - Non-Hillside
Work Description
Grading for site drainage
Permit Issued
Issued on 10/12/2021
Issuing Office
Current Status
Permit Finaled on 11/18/2022

Permit Application Status History

Submitted 7/22/2021 APPLICANT
Assigned to Plan Check Engineer 8/5/2021 RARES BODEA
Corrections Issued 8/20/2021 RARES BODEA
Quality Review Completed 9/9/2021 STEVEN KIM
Plan Check Approved 10/1/2021 RARES BODEA
Issued 10/12/2021 APPLICANT
Permit Finaled 11/17/2022 JONATHAN HOM

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/30/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 8/31/2021 LEE GUILBEAUX
Low Impact Development Cleared 9/29/2021 ANDRES COVARRUBIAS

Contact Information

Contractor Paragon Construction Company Llc; Lic. No.: 1072485-B 2656 E DENIM TRL      SAN TAN VALLEY, AZ 85143
Engineer Labib,, Youhanna T; Lic. No.: S4549 319 MAIN STREET      EL SEGUNDO, CA 90245

Inspector Information

ALEXANDER HELFER, (818) 374-4354 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Drainage Devices/Catch Basin 12/17/2021 Partial Approval BRIAN MILLER
Drainage Devices/Catch Basin 12/27/2021 Not Ready for Inspection TIMOTHY POWELL
Drainage Devices/Catch Basin 12/29/2021 Not Ready for Inspection BRIAN MILLER
Drainage Devices/Catch Basin 1/6/2022 Partial Approval BRIAN MILLER
Drainage Devices/Catch Basin 1/12/2022 Partial Approval BRIAN MILLER
Drainage Devices/Catch Basin 1/13/2022 Partial Approval BRIAN MILLER
Drainage Devices/Catch Basin 1/18/2022 Partial Approval BRIAN MILLER
Drainage Devices/Catch Basin 1/19/2022 Partial Approval BRIAN MILLER
Drainage Devices/Catch Basin 1/21/2022 Partial Approval BRIAN MILLER
Drainage Devices/Catch Basin 1/26/2022 Partial Approval BRIAN MILLER
Drainage Devices/Catch Basin 2/17/2022 Partial Approval BRIAN MILLER
Excavation 2/23/2022 Not Ready for Inspection BRIAN MILLER
Bottom/Toe 8/11/2022 Not Ready for Inspection MANUEL TEJADA
Final 8/11/2022 Corrections Issued MANUEL TEJADA
Rough 8/11/2022 Not Ready for Inspection MANUEL TEJADA
Bottom/Toe 8/23/2022 Not Ready for Inspection LANNY MERRICK
Final 8/23/2022 Not Ready for Inspection LANNY MERRICK
Rough 8/23/2022 Not Ready for Inspection LANNY MERRICK
Bottom/Toe 11/17/2022 Approved JONATHAN HOM
Final 11/17/2022 Permit Finaled JONATHAN HOM
Rough 11/17/2022 Approved JONATHAN HOM