3818 N GLENEAGLES DR 91356

Certificate Information: 3818 N GLENEAGLES DR 91356

Application / Permit
21030-20000-03977
Plan Check / Job No.
B21VN07710
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
GRADING & EXCAVATION FOR NEW RETAINING WALL AND NEW POOL/SPA CUT: 46.5 CY (36.5CY POOL + 10 CY WALL) FILL: 2 CY EXPORT: 44.4 CY IMPORT: 0 CY
Permit Issued
Issued on 3/10/2022
Issuing Office
Current Status
Permit Finaled on 12/12/2023

Permit Application Status History

Submitted 6/16/2021 APPLICANT
Assigned to Plan Check Engineer 7/22/2021 COLIN LOREDO
Corrections Issued 8/5/2021 COLIN LOREDO
Quality Review Completed 8/18/2021 OMID HEDAYAT
Building Plans Picked Up 8/20/2021 APPLICANT
Plan Check Approved 3/3/2022 COLIN LOREDO
Issued 3/10/2022 APPLICANT
Permit Finaled 12/12/2023 ROBERT PINA

Permit Application Clearance Information

Specific Plan Cleared 10/26/2021 OLGA AYALA
ZA Case Cleared 10/26/2021 OLGA AYALA
ZA Case Cleared 10/26/2021 OLGA AYALA
Grading Pre-Inspection Cleared 2/3/2022 PATRICK MISCHLICH

Contact Information

Contractor Owner-Builder       ,
Engineer Hayrikian,, Arsham; Lic. No.: C91446 1732 CAMULOS AVE      GLENDALE, CA 91208
Engineer Karapetian,, Arbi; Lic. No.: C79953 21520 BURBANK BLVD APT 219      WOODLAND HILLS, CA 91367
Geologist Minas,, Shant; Lic. No.: EG2607 566 RIVERDALE DRIVE      GLENDALE, CA 91204

Inspector Information

MANUEL TEJADA, (818) 374-4339 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Bottom/Toe 4/26/2022 Approved LANNY MERRICK
Excavation 4/26/2022 Partial Approval LANNY MERRICK
Excavation 4/28/2022 Not Ready for Inspection LANNY MERRICK
Rough 5/4/2022 Partial Approval MANUEL TEJADA
Rough 5/10/2022 Partial Approval LANNY MERRICK
Sub-Drain 5/10/2022 Partial Approval LANNY MERRICK
Rough 5/12/2022 Partial Approval LANNY MERRICK
Sub-Drain 6/24/2022 Approved LANNY MERRICK
Final 12/6/2023 Not Ready for Inspection ROBERT PINA
Rough 12/6/2023 Not Ready for Inspection ROBERT PINA
Final 12/12/2023 Permit Finaled ROBERT PINA
Rough 12/12/2023 Approved ROBERT PINA