5032 N DON PIO DR 91364
Certificate Information: 5032 N DON PIO DR 91364
- Application / Permit
- 21030-20000-03913
- Plan Check / Job No.
- B21VN07582
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- SITE PREP. TO CUT OUT GRADE FROM REAR FOR NEW 2 STORY SINGLE FAMILY DWELLING AND BASEMENT
- Permit Issued
- Issued on 7/6/2022
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 10/2/2023
Permit Application Status History
| Submitted | 6/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2021 | PETER MOSESIAN |
| Corrections Issued | 8/1/2021 | PETER MOSESIAN |
| Quality Review Completed | 8/18/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 8/20/2021 | APPLICANT |
| Plan Check Approved | 7/6/2022 | PETER MOSESIAN |
| Issued | 7/6/2022 | APPLICANT |
| Permit Finaled-Status Void | 9/28/2023 | ROBERT PINA |
| Permit Finaled | 9/28/2023 | ROBERT PINA |
| Re-Activate Permit | 9/29/2023 | ROBERT PINA |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/6/2022 | PETER MOSESIAN |
Contact Information
| Architect | Bagheri-Fard,, Karim; Lic. No.: C29280 | 4516 SAN TAELA COURT WOODLAND HILLS, CA 91364 |
| Contractor | Owner-Builder | , |
| Engineer | Kamboj,, Naresh Chande; Lic. No.: C21893 | 7838 QUIMBY AVE CANOGA PARK, CA 91304 |
| Engineer | Minas,, Caro Jolfaie; Lic. No.: GE601 | 4742 SAN FERNANDO RD GLENDALE, CA 91204 |
Inspector Information
| MANUEL TEJADA, (818) 374-4339 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 7/15/2022 | Partial Approval | LANNY MERRICK |
| Excavation | 8/31/2022 | Partial Approval | LANNY MERRICK |
| Sub-Drain | 10/4/2022 | Approved | VASIL MIHALEV |
| SWPPP-Const. Storm Water | 10/5/2022 | Not Required | LANNY MERRICK |
| Drainage Devices/Catch Basin | 5/24/2023 | Partial Approval | ROBERT PINA |
| Fill/Backfill | 5/24/2023 | Corrections Issued | ROBERT PINA |
| Bottom/Toe | 5/26/2023 | Approved | ROBERT PINA |
| Final | 8/29/2023 | Not Ready for Inspection | ROBERT PINA |
| Rough | 8/29/2023 | Not Ready for Inspection | ROBERT PINA |
| Final | 9/28/2023 | Permit Finaled | ROBERT PINA |
| Rough | 9/28/2023 | Approved | ROBERT PINA |