15620 W WOODVALE ROAD 91436
Certificate Information: 15620 W WOODVALE ROAD 91436
- Application / Permit
- 21030-20000-03624
- Plan Check / Job No.
- B21VN06998
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- SITE GRADING FOR (N) 2-STORY SFD W/ ATTACHED GARAGE & BASEMENT & 10FT HIGH MAX RETAINING WALL -- HILLSIDE GRADING AREA
- Permit Issued
- Issued on 3/15/2022
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 3/28/2024
Permit Application Status History
| Submitted | 6/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2021 | NILOOFAR MEHRAIN |
| Corrections Issued | 6/22/2021 | NILOOFAR MEHRAIN |
| Quality Review Completed | 6/23/2021 | CHON CHIO KUO |
| Building Plans Picked Up | 6/25/2021 | APPLICANT |
| Applicant returned to address corrections | 9/16/2021 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 9/21/2021 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 12/22/2021 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 1/20/2022 | NILOOFAR MEHRAIN |
| Plan Check Approved | 3/10/2022 | NILOOFAR MEHRAIN |
| Issued | 3/15/2022 | APPLICANT |
| Permit Finaled | 3/27/2024 | ROBERT PINA |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/29/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 6/30/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Luxe Development Inc; Lic. No.: 993473-B | 329 N WETHERLY DRIVE #205 BEVERLY HILLS, CA 90211 |
| Engineer | Pirbadian,, Amir; Lic. No.: C72413 | 5435 BALBOA BLVD 214 ENCINO, CA 91342 |
Inspector Information
| MANUEL TEJADA, (818) 374-4339 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drainage Devices/Catch Basin | 5/9/2022 | Partial Approval | MANUEL TEJADA |
| Sub-Drain | 5/9/2022 | Partial Approval | MANUEL TEJADA |
| Sub-Drain | 6/16/2022 | Partial Approval | LANNY MERRICK |
| Sub-Drain | 7/29/2022 | Approved | LANNY MERRICK |
| Bottom/Toe | 2/23/2024 | Corrections Issued | ROBERT PINA |
| Final | 2/23/2024 | Not Ready for Inspection | ROBERT PINA |
| Rough | 2/23/2024 | Not Ready for Inspection | ROBERT PINA |
| Approved Compaction Report | 3/22/2024 | Approved | ROBERT PINA |
| Bottom/Toe | 3/27/2024 | Approved | ROBERT PINA |
| Final | 3/27/2024 | Permit Finaled | ROBERT PINA |
| Rough | 3/27/2024 | Approved | ROBERT PINA |