550 S WOODRUFF AVE 90024

Certificate Information: 550 S WOODRUFF AVE 90024

Application / Permit
21030-20000-03514
Plan Check / Job No.
B21VN06757
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
GRADING PERMIT FOR SITE PREP AND EXCAVATION FOR PROPOSED SFD W/ BASEMENT [ABC SLOT-CUT EXCAVATION METHOD FOR SFD LOWER FLOOR]
Permit Issued
Issued on 8/4/2022
Issuing Office
Valley
Current Status
Permit Finaled on 7/23/2025

Permit Application Status History

Submitted 6/1/2021 APPLICANT
Assigned to Plan Check Engineer 7/1/2021 SEAN SHAHMIRI
Corrections Issued 7/3/2021 SEAN SHAHMIRI
Quality Review Completed 7/9/2021 OMID HEDAYAT
Building Plans Picked Up 7/12/2021 APPLICANT
Applicant returned to address corrections 6/16/2022 SEAN SHAHMIRI
Applicant returned to address corrections 7/20/2022 SEAN SHAHMIRI
Plan Check Approved 7/20/2022 SEAN SHAHMIRI
No Progress 7/20/2022 SEAN SHAHMIRI
Plan Check Approved 7/21/2022 SEAN SHAHMIRI
Issued 8/4/2022 APPLICANT
Permit Finaled 7/23/2025 LANNY MERRICK

Permit Application Clearance Information

Excavation more than 5-ft deep Cleared 8/1/2022 CALOSHA APPROVED

Contact Information

Contractor Hilliard J Stuart Inc; Lic. No.: 182031-B 7136 HASKELL AVENUE SUITE 109      VAN NUYS, CA 91406
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401
Engineer Rowlands,, James; Lic. No.: GE740 10954 SANTA MONICA BLVD      LOS ANGELES, CA 90025

Inspector Information

JOHNNY MIRANDA, (310) 914-3937 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 2/3/2023 Partial Inspection MATTHEW JENKINS
Drainage Devices/Catch Basin 2/6/2023 Partial Approval MATTHEW JENKINS
Sub-Drain 2/9/2023 Partial Approval MATTHEW JENKINS
Excavation 5/8/2023 Partial Approval RUSSELL BONVOULOIR
Approved Compaction Report 5/24/2023 Approved VASIL MIHALEV
Rough 8/24/2023 Corrections Issued MATTHEW JENKINS
Rough 10/10/2023 Partial Approval MATTHEW JENKINS
Excavation 10/16/2023 Partial Inspection MATTHEW JENKINS
Bottom/Toe 6/27/2025 Not Ready for Inspection AL GAMBLE
Final 6/27/2025 Not Ready for Inspection AL GAMBLE
Rough 6/27/2025 Not Ready for Inspection AL GAMBLE
Bottom/Toe 7/21/2025 Partial Inspection AL GAMBLE
Final 7/21/2025 Not Ready for Inspection AL GAMBLE
Rough 7/21/2025 Not Ready for Inspection AL GAMBLE
Initial Grading 7/22/2025 Not Ready for Inspection AL GAMBLE
Bottom/Toe 7/23/2025 Approved LANNY MERRICK
Final 7/23/2025 Permit Finaled LANNY MERRICK
Rough 7/23/2025 Approved LANNY MERRICK