550 N HANLEY AVE 90049

Certificate Information: 550 N HANLEY AVE 90049

Application / Permit
21030-20000-03082
Plan Check / Job No.
B21VN05789
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
SITE PREPARATION
Permit Issued
Issued on 8/16/2021
Issuing Office
Valley
Current Status
Permit Finaled on 4/1/2023

Permit Application Status History

Submitted 5/11/2021 APPLICANT
Assigned to Plan Check Engineer 5/26/2021 RARES BODEA
Corrections Issued 5/29/2021 RARES BODEA
Quality Review Completed 6/8/2021 STEVEN KIM
Building Plans Picked Up 6/11/2021 APPLICANT
Applicant returned to address corrections 7/14/2021 RARES BODEA
Applicant returned to address corrections 8/10/2021 RARES BODEA
Plan Check Approved 8/16/2021 RARES BODEA
Issued 8/16/2021 APPLICANT
Permit Finaled 3/31/2023 CHARLES POWELL

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 8/19/2021 Corrections Issued MATTHEW JENKINS
Bottom/Toe 9/1/2021 Approved MATTHEW JENKINS
Sub-Drain 12/15/2021 Partial Approval CHARLES POWELL
Sub-Drain 3/3/2022 Partial Approval CHARLES POWELL
Sub-Drain 6/2/2022 Partial Approval TIMOTHY POWELL
Approved Compaction Report 7/29/2022 Partial Approval CHARLES POWELL
Final 9/27/2022 Not Ready for Inspection CHARLES POWELL
Rough 9/27/2022 Not Ready for Inspection CHARLES POWELL
Approved Compaction Report 12/7/2022 Approved CHARLES POWELL
Final 2/14/2023 Not Ready for Inspection CHARLES POWELL
Rough 2/14/2023 Not Ready for Inspection CHARLES POWELL
Final 3/31/2023 Permit Finaled CHARLES POWELL
Rough 3/31/2023 Approved CHARLES POWELL