21929 W ROSCOE BLVD 91304

Certificate Information: 21929 W ROSCOE BLVD 91304

Application / Permit
21030-20000-03036
Plan Check / Job No.
B21VN05642
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(60) Grading - Non-Hillside
Work Description
SITE PREP FOR (N) CAFE -- NON HILLSIDE GRADING AREA
Permit Issued
Issued on 5/17/2022
Issuing Office
Metro
Current Status
Permit Finaled on 7/25/2023

Permit Application Status History

Submitted 5/13/2021 APPLICANT
Assigned to Plan Check Engineer 6/17/2021 ALYSSA N NARCISO
Corrections Issued 6/23/2021 ALYSSA N NARCISO
Quality Review Completed 6/30/2021 STEVEN KIM
Building Plans Picked Up 7/7/2021 APPLICANT
Applicant returned to address corrections 9/9/2021 NILOOFAR MEHRAIN
Applicant returned to address corrections 10/21/2021 NILOOFAR MEHRAIN
Applicant returned to address corrections 3/3/2022 NILOOFAR MEHRAIN
Plan Check Approved 5/5/2022 NILOOFAR MEHRAIN
Issued 5/17/2022 APPLICANT
Permit Finaled-Status Void 2/9/2023 ROBERT PINA
Re-Activate Permit 2/17/2023 ROBERT PINA
Permit Finaled 7/25/2023 BRIAN MILLER

Permit Application Clearance Information

Low Impact Development Cleared 1/27/2022 ANDRES COVARRUBIAS
Miscellaneous Cleared 4/8/2022 STEVEN WECHSLER
ZA Case Cleared 4/8/2022 STEVEN WECHSLER
ZA Case Cleared 4/8/2022 STEVEN WECHSLER

Contact Information

Architect Mc, Kently, Kenneth; Lic. No.: C19257 1708 LAS FLORES DRIVE      GLENDALE, CA 91207
Contractor Cirks Construction Inc; Lic. No.: 763589-B 1927 N GLASSELL ST      ORANGE, CA 92865
Engineer Black,, Ian Robert; Lic. No.: S5505 19401 OLANA LN      HUNTINGTON BEACH, CA 92646
Engineer Jiang,, Clarence Tzu-Wei; Lic. No.: GE2477 PO BOX 1891      WEST COVINA, CA 91793
Engineer Salem,, Rifaat Sammy; Lic. No.: GE2549 4195 W SAMPLE AVE      FRESNO, CA 93722

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 5/20/2022 Approved BRIAN MILLER
Bottom/Toe 5/24/2022 Conditional Approval BRIAN MILLER
Fill/Backfill 5/27/2022 Partial Approval BRIAN MILLER
Drainage Devices/Catch Basin 6/8/2022 Partial Approval BRIAN MILLER
Sub-Drain 7/15/2022 Partial Approval BRIAN MILLER
Drainage Devices/Catch Basin 7/27/2022 Approved LANNY MERRICK
Approved Compaction Report 7/29/2022 Corrections Issued BRIAN MILLER
Drainage Devices/Catch Basin 8/2/2022 Partial Approval BRIAN MILLER
Deputy Other (see comments) 9/13/2022 Approved MANUEL TEJADA
Drainage Devices/Catch Basin 12/19/2022 Approved ALEXANDER HELFER
Bottom/Toe 2/9/2023 Approved ROBERT PINA
Final 2/9/2023 Partial Inspection ROBERT PINA
Rough 2/9/2023 Approved ROBERT PINA
Approved Compaction Report 2/22/2023 Approved BRIAN MILLER
Approved Compaction Report 2/27/2023 Approved BRIAN MILLER
Final 7/25/2023 Permit Finaled BRIAN MILLER