1822 N VISTA ST 90046

Certificate Information: 1822 N VISTA ST 90046

Application / Permit
21030-20000-01807
Plan Check / Job No.
B21VN03229
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
GRADING EXCAVATION AND BACKFILL FOR RETAINING WALLS, BASEMENT, SITE PREP
Permit Issued
Issued on 8/11/2022
Issuing Office
Valley
Current Status
Permit Finaled on 3/14/2024

Permit Application Status History

Submitted 3/18/2021 APPLICANT
Assigned to Plan Check Engineer 3/25/2021 SELLA BENYAMIN
Corrections Issued 3/31/2021 SELLA BENYAMIN
Quality Review Completed 4/5/2021 STEVEN KIM
Building Plans Picked Up 9/15/2021 APPLICANT
Applicant returned to address corrections 4/18/2022 SELLA BENYAMIN
Applicant returned to address corrections 6/8/2022 SELLA BENYAMIN
Plan Check Approved 7/28/2022 SELLA BENYAMIN
Issued 8/11/2022 APPLICANT
Permit Finaled 3/13/2024 ALEXANDER HELFER

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ROBERT PINA, (213) 482-0404 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 8/30/2022 Approved ALEXANDER HELFER
Excavation 9/16/2022 Approved ALEXANDER HELFER
Sub-Drain 2/22/2023 Approved ALEXANDER HELFER
Bottom/Toe 4/13/2023 Not Ready for Inspection ALEXANDER HELFER
Bottom/Toe 4/17/2023 Partial Approval ALEXANDER HELFER
Excavation 4/19/2023 Approved ALEXANDER HELFER
Approved Compaction Report 5/16/2023 Approved ALEXANDER HELFER
Bottom/Toe 3/4/2024 Not Ready for Inspection ALEXANDER HELFER
Final 3/4/2024 Not Ready for Inspection ALEXANDER HELFER
Rough 3/4/2024 Not Ready for Inspection ALEXANDER HELFER
Bottom/Toe 3/5/2024 Approved ALEXANDER HELFER
Final 3/5/2024 Not Ready for Inspection ALEXANDER HELFER
Rough 3/5/2024 Not Ready for Inspection ALEXANDER HELFER
Final 3/13/2024 Permit Finaled ALEXANDER HELFER
Rough 3/13/2024 Approved ALEXANDER HELFER