1738 S WOOSTER ST 90035
Certificate Information: 1738 S WOOSTER ST 90035
- Application / Permit
- 21030-20000-01791
- Plan Check / Job No.
- B21VN03195
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- GRADING FOR BASEMENT RET. WALL EXCAVATION & BACKFILLL, POOL TO BE BACKFILLED AND SHELL TO BE REMOVED PER P/BC 2020-111
- Permit Issued
- Issued on 9/20/2021
- Issuing Office
- Current Status
- Permit Finaled on 7/29/2024
Permit Application Status History
| Submitted | 3/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2021 | MARVEL DELACRUZ |
| Corrections Issued | 4/26/2021 | MARVEL DELACRUZ |
| Quality Review Completed | 5/3/2021 | STEVEN KIM |
| Applicant returned to address corrections | 6/16/2021 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 7/7/2021 | MARVEL DELACRUZ |
| Plan Check Approved | 8/27/2021 | MARVEL DELACRUZ |
| Issued | 9/20/2021 | APPLICANT |
| Permit Finaled | 7/26/2024 | ALEXANDER HELFER |
Permit Application Clearance Information
| Excavation more than 5-ft deep | Cleared | 9/1/2021 | CALOSHA APPROVED |
Contact Information
| Contractor | Gramercy Group Design And Build Inc The; Lic. No.: 943331-B | 149 S BARRINGTON AVENUE SUITE 671 BRENTWOOD, CA 90049 |
| Engineer | Babayan,, Raffi Samuel; Lic. No.: C72168 | 7718 DAY STREET LOS ANGELES, CA 91042 |
| Engineer | Yamini,, Soly; Lic. No.: C33719 | 540 WARNER AVE LOS ANGELES, CA 90024 |
Inspector Information
| AL GAMBLE, (213) 482-0403 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Bottom/Toe | 9/28/2021 | Partial Approval | ALEXANDER HELFER |
| Deputy Grading | 10/21/2021 | Conditional Approval | LANNY MERRICK |
| Deputy Grading | 10/22/2021 | Conditional Approval | LANNY MERRICK |
| Bottom/Toe | 2/22/2022 | Partial Approval | LANNY MERRICK |
| Sub-Drain | 8/23/2022 | Partial Approval | MATTHEW JENKINS |
| Bottom/Toe | 9/28/2022 | Partial Approval | MATTHEW JENKINS |
| Excavation | 9/28/2022 | Partial Inspection | MATTHEW JENKINS |
| Bottom/Toe | 9/30/2022 | Partial Approval | MATTHEW JENKINS |
| Sub-Drain | 1/4/2023 | Partial Approval | JONATHAN HOM |
| Approved Compaction Report | 2/21/2024 | Approved | MICHAEL TEMPLE |
| Bottom/Toe | 7/26/2024 | Approved | ALEXANDER HELFER |
| Final | 7/26/2024 | Permit Finaled | ALEXANDER HELFER |