200 N TOYOPA DR 90272

Certificate Information: 200 N TOYOPA DR 90272

Application / Permit
21030-20000-01601
Plan Check / Job No.
B21VN02874
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
GRADING EXCAVATION AND BACKFILL OF RETAINING WALLS & SFD BASEMENT. (2,053 CY.)
Permit Issued
Issued on 10/19/2021
Issuing Office
Current Status
Issued on 10/19/2021

Permit Application Status History

Submitted 3/11/2021 APPLICANT
Assigned to Plan Check Engineer 3/18/2021 TROY DEGUZMAN
Corrections Issued 3/20/2021 TROY DEGUZMAN
Quality Review Completed 4/1/2021 CHON CHIO KUO
Applicant returned to address corrections 7/22/2021 TROY DEGUZMAN
Applicant returned to address corrections 7/23/2021 TROY DEGUZMAN
Plan Check Approved 9/30/2021 TROY DEGUZMAN
Issued 10/19/2021 APPLICANT

Permit Application Clearance Information

Excavation more than 5-ft deep Cleared 7/23/2021 CALOSHA APPROVED
GPI Written Notices Cleared 7/23/2021 TROY DEGUZMAN
Grading Pre-Inspection Cleared 7/23/2021 TROY DEGUZMAN

Contact Information

Contractor Home Base Construction; Lic. No.: 868641-B 1431 DENTRO DE LOMAS      BONSALL, CA 92003
Engineer Lau,, David Harkwong; Lic. No.: C34961 12467 W WASHINGTON BLVD      LOS ANGELES, CA 90066
Engineer White,, William Michael; Lic. No.: C62111 19619 MATHILDE LN      SAUGUS, CA 91350

Inspector Information

RUSSELL BONVOULOIR, (310) 914-3899 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 10/14/2022 Partial Inspection MATTHEW JENKINS
Rough 10/27/2022 Partial Inspection TIMOTHY POWELL
Rough 11/2/2022 Partial Inspection TIMOTHY POWELL
Deputy Grading 11/8/2022 No Access for Inspection TIMOTHY POWELL
Deputy Grading 11/14/2022 Conditional Approval TIMOTHY POWELL
Deputy Grading 11/15/2022 Conditional Approval TIMOTHY POWELL
Deputy Grading 11/17/2022 Conditional Approval TIMOTHY POWELL
Deputy Grading 11/18/2022 Conditional Approval MICHAEL TEMPLE
Deputy Grading 11/23/2022 Approved JONATHAN HOM
Deputy Grading 12/7/2022 Conditional Approval MICHAEL TEMPLE
Deputy Grading 12/14/2022 Partial Approval MICHAEL TEMPLE
Deputy Grading 1/26/2023 Approved VASIL MIHALEV
Sub-Drain 5/7/2024 Partial Approval JOHNNY MIRANDA
Sub-Drain 5/15/2024 Approved VASIL MIHALEV
Sub-Drain 9/3/2024 Partial Approval JOHNNY MIRANDA
Special/Order Compliance 9/18/2024 Not Ready for Inspection VASIL MIHALEV
Special/Order Compliance 9/25/2024 Approved VASIL MIHALEV
Deputy Grading 10/8/2024 Conditional Approval JOHNNY MIRANDA
Fill/Backfill 10/16/2024 Not Ready for Inspection VASIL MIHALEV
Rough 10/16/2024 Corrections Issued VASIL MIHALEV
Sub-Drain 10/16/2024 Not Ready for Inspection VASIL MIHALEV
Approved Compaction Report 10/24/2024 Corrections Issued MATTHEW JENKINS
Sub-Drain 4/3/2025 Partial Approval JOHNNY MIRANDA
Special/Order Compliance 12/19/2025 Corrections Issued BOBBY KEY