3935 W 8TH ST 1-19 90005

Certificate Information: 3935 W 8TH ST 1-19 90005

Application / Permit
21030-20000-01512
Plan Check / Job No.
B21VN02754
Group
Building
Type
Grading
Sub-Type
Apartment
Primary Use
(60) Grading - Non-Hillside
Work Description
GRADING - SIDE PREP, BACKFILL
Permit Issued
Issued on 12/1/2021
Issuing Office
Valley
Current Status
Issued on 12/1/2021

Permit Application Status History

Submitted 3/8/2021 APPLICANT
Assigned to Plan Check Engineer 3/31/2021 CHON CHIO KUO
Corrections Issued 4/5/2021 CHON CHIO KUO
Quality Review Completed 4/9/2021 STEVEN KIM
Applicant returned to address corrections 7/1/2021 CHON CHIO KUO
Plan Check Approved 11/2/2021 SELLA BENYAMIN
Issued 12/1/2021 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/14/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 5/17/2021 JEANIE LAM
Highway dedication Cleared 6/28/2021 CECILIO NAVARRO
ZA Case Cleared 6/30/2021 LAUREN PADICK
Excavation more than 5-ft deep Cleared 11/2/2021 CALOSHA APPROVED
Low Impact Development Cleared 11/4/2021 MARTIN FRAGOSO

Contact Information

Contractor Schon Tepler Construction, Inc; Lic. No.: 969338-B 6250 HOLLYWOOOD BLVD 10M      LOS ANGELES, CA 90028
Engineer Pirbadian,, Amir; Lic. No.: C72413 5435 BALBOA BLVD 214      ENCINO, CA 91342
Engineer Walter,, Scott John; Lic. No.: GE2476 14428 HAMLIN ST STE 200      VAN NUYS, CA 91401

Inspector Information

AL GAMBLE, (213) 482-0403 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 1/24/2022 Approved LANNY MERRICK
Initial Grading 3/10/2022 Partial Inspection LANNY MERRICK
Fill/Backfill 3/14/2022 Conditional Approval LANNY MERRICK
Bottom/Toe 3/24/2022 Corrections Issued ROBERT HUGHES
Initial Grading 3/25/2022 Not Ready for Inspection LANNY MERRICK
Deputy Grading 4/1/2022 Conditional Approval LANNY MERRICK
Rough 4/1/2022 Conditional Approval LANNY MERRICK
Initial Grading 4/5/2022 Partial Approval LANNY MERRICK
Initial Grading 4/25/2022 Partial Inspection MATTHEW JENKINS
Bottom/Toe 4/28/2022 Approved ALEXANDER HELFER
Approved Compaction Report 5/5/2022 Corrections Issued MATTHEW JENKINS
Approved Compaction Report 5/18/2022 Approved MATTHEW JENKINS
Sub-Drain 6/28/2022 Partial Inspection MATTHEW JENKINS
Sub-Drain 7/21/2022 Approved ALEXANDER HELFER
Sub-Drain 9/29/2022 Partial Approval ALEXANDER HELFER