13822 W DAVANA TER 91423
Certificate Information: 13822 W DAVANA TER 91423
- Application / Permit
- 21030-20000-01373
- Plan Check / Job No.
- B21VN02520
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- GRADING EXCAVATION FOR PROPERTY RETAINING WALL. (180 CY).
- Permit Issued
- Issued on 7/13/2021
- Issuing Office
- Current Status
- Permit Finaled on 7/11/2022
Permit Application Status History
| Submitted | 3/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2021 | TROY DEGUZMAN |
| Corrections Issued | 3/26/2021 | TROY DEGUZMAN |
| Quality Review Completed | 4/5/2021 | CHON CHIO KUO |
| Applicant returned to address corrections | 6/15/2021 | TROY DEGUZMAN |
| Plan Check Approved | 7/13/2021 | TROY DEGUZMAN |
| Issued | 7/13/2021 | APPLICANT |
| Permit Finaled | 7/11/2022 | MANUEL TEJADA |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/26/2021 | TROY DEGUZMAN |
| GPI Written Notices | Cleared | 6/15/2021 | TROY DEGUZMAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Alferez,, Vicente Narvaez; Lic. No.: C53875 | 460 E CARSON PLAZA DR STE 212 CARSON, CA 90746 |
| Engineer | Holt,, Justin Denver; Lic. No.: C71452 | 702 GREENBRIAR AVE SIMI VALLEY, CA 93065 |
| Geologist | Rahimikian,, Pedram; Lic. No.: EG2683 | 5841 ETIWANDA AVE TARZANA, CA 91356 |
Inspector Information
| MATTHEW JENKINS, (818) 374-4357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation | 7/26/2021 | Conditional Approval | MANUEL TEJADA |
| Bottom/Toe | 7/29/2021 | Partial Approval | MANUEL TEJADA |
| Excavation | 8/6/2021 | Corrections Issued | MANUEL TEJADA |
| Excavation | 8/11/2021 | Partial Approval | MANUEL TEJADA |
| Excavation | 8/27/2021 | Partial Approval | ALEXANDER ANDREWS |
| Excavation | 8/31/2021 | Not Ready for Inspection | TIMOTHY POWELL |
| Excavation | 9/16/2021 | Corrections Issued | TIMOTHY POWELL |
| Approved Compaction Report | 10/22/2021 | Approved | TIMOTHY POWELL |
| Bottom/Toe | 7/11/2022 | Approved | MANUEL TEJADA |
| Final | 7/11/2022 | Permit Finaled | MANUEL TEJADA |
| Rough | 7/11/2022 | Approved | MANUEL TEJADA |