1665 N MANDEVILLE CANYON ROAD 90049
Certificate Information: 1665 N MANDEVILLE CANYON ROAD 90049
- Application / Permit
- 21030-20000-01197
- Plan Check / Job No.
- B21VN02232
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- GRADING EXCAVATION FOR SFD. (2,110 CY)
- Permit Issued
- Issued on 9/15/2021
- Issuing Office
- Current Status
- Permit Finaled on 1/25/2023
Permit Application Status History
| Submitted | 3/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2021 | TROY DEGUZMAN |
| Corrections Issued | 3/10/2021 | TROY DEGUZMAN |
| Quality Review Completed | 3/22/2021 | OMID HEDAYAT |
| Applicant returned to address corrections | 5/18/2021 | TROY DEGUZMAN |
| Applicant returned to address corrections | 5/19/2021 | TROY DEGUZMAN |
| Applicant returned to address corrections | 8/25/2021 | TROY DEGUZMAN |
| Plan Check Approved | 9/2/2021 | TROY DEGUZMAN |
| Issued | 9/15/2021 | APPLICANT |
| Permit Finaled | 1/24/2023 | RUSSELL BONVOULOIR |
Permit Application Clearance Information
| Watercourse | Cleared | 5/11/2021 | MAHELET GEBEYHU |
| GPI Written Notices | Cleared | 5/18/2021 | TROY DEGUZMAN |
| Grading Pre-Inspection | Cleared | 5/18/2021 | TROY DEGUZMAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/13/2021 | TRACY TATE |
Contact Information
| Contractor | Blue Label Construction Inc; Lic. No.: 972011-B | 1448 15TH STREET #102 SANTA MONICA, CA 90404 |
| Engineer | Danz,, Joshua Franklin; Lic. No.: C84764 | 1164 ELDERBERRY CIRCLE FOLSOM, CA 95630 |
| Engineer | Padilla,, Juan C; Lic. No.: C79760 | 647 ERBES ROAD THOUSAND OAKS, CA 91362 |
| Engineer | Tani,, Jason Yukio; Lic. No.: C58271 | 5296 VIA PATRICIA THOUSAND OAKS, CA 91320 |
| Geologist | Irvine,, Jon A; Lic. No.: EG1691 | 819 W HERITAGE OAK CT ALTADENA, CA 91001 |
Inspector Information
| RAMAZANALI ALMASI, (310) 914-3899 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 9/17/2021 | Partial Inspection | MATTHEW JENKINS |
| Bottom/Toe | 9/20/2021 | Partial Inspection | MATTHEW JENKINS |
| Initial Grading | 9/20/2021 | Partial Approval | MATTHEW JENKINS |
| Initial Grading | 9/24/2021 | Partial Approval | MATTHEW JENKINS |
| Bottom/Toe | 9/28/2021 | Partial Approval | MATTHEW JENKINS |
| Excavation | 10/13/2021 | Partial Approval | MATTHEW JENKINS |
| Rough | 1/21/2022 | Partial Inspection | MATTHEW JENKINS |
| Rough | 1/27/2022 | Partial Inspection | MATTHEW JENKINS |
| Sub-Drain | 3/4/2022 | Partial Approval | CHARLES POWELL |
| Bottom/Toe | 4/29/2022 | Not Ready for Inspection | TIMOTHY POWELL |
| Excavation | 4/29/2022 | Not Ready for Inspection | TIMOTHY POWELL |
| Bottom/Toe | 5/16/2022 | Partial Approval | MATTHEW JENKINS |
| Excavation | 5/16/2022 | Partial Approval | MATTHEW JENKINS |
| Approved Compaction Report | 7/21/2022 | Approved | TIMOTHY POWELL |
| Bottom/Toe | 12/9/2022 | Approved | TIMOTHY POWELL |
| Final | 12/9/2022 | Not Ready for Inspection | TIMOTHY POWELL |
| Rough | 12/9/2022 | Approved | TIMOTHY POWELL |
| Final | 12/21/2022 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| Final | 1/18/2023 | Partial Inspection | RUSSELL BONVOULOIR |
| Final | 1/24/2023 | Permit Finaled | RUSSELL BONVOULOIR |