755 N NAPOLI DR 90272

Certificate Information: 755 N NAPOLI DR 90272

Application / Permit
21030-20000-01169
Plan Check / Job No.
B21VN02188
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
excavation for basment and rw backfill and site prep
Permit Issued
Issued on 7/1/2021
Issuing Office
Current Status
Permit Finaled on 10/20/2023

Permit Application Status History

Submitted 2/26/2021 APPLICANT
Assigned to Plan Check Engineer 3/4/2021 MOHAMMAD ESMAILI
Corrections Issued 3/11/2021 MOHAMMAD ESMAILI
Quality Review Completed 3/12/2021 OMID HEDAYAT
Building Plans Picked Up 3/17/2021 APPLICANT
Applicant returned to address corrections 6/21/2021 MOHAMMAD ESMAILI
Plan Check Approved 6/21/2021 MOHAMMAD ESMAILI
Issued 7/1/2021 APPLICANT
Permit Finaled 10/19/2023 JOHNNY MIRANDA

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/23/2021 CATHERINE ADROVER
Low Impact Development Cleared 6/11/2021 ORVAL HERNANDEZ-MARCI
Excavation more than 5-ft deep Cleared 6/21/2021 CALOSHA APPROVED
Grading Pre-Inspection Cleared 6/21/2021 MOHAMMAD ESMAILI
Roof/Waste drainage to street Cleared 6/23/2021 DINAH GARIN

Contact Information

Contractor Williams Craig R Construction Inc; Lic. No.: 479539-B 9100 WILSHIRE BLVD   STE 503E    BEVERLY HILLS, CA 90212
Engineer Tani,, Jason Yukio; Lic. No.: C58271 5296 VIA PATRICIA      THOUSAND OAKS, CA 91320

Inspector Information

RUSSELL BONVOULOIR, (310) 914-3899 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 7/19/2021 Approved MATTHEW JENKINS
Sub-Drain 9/22/2021 Partial Inspection MATTHEW JENKINS
Rough 9/23/2021 Corrections Issued MATTHEW JENKINS
Bottom/Toe 1/12/2022 Partial Approval MATTHEW JENKINS
Bottom/Toe 9/7/2023 No Access for Inspection JOHNNY MIRANDA
Final 9/7/2023 No Access for Inspection JOHNNY MIRANDA
Rough 9/7/2023 No Access for Inspection JOHNNY MIRANDA
Bottom/Toe 9/25/2023 Not Ready for Inspection JOHNNY MIRANDA
Final 9/25/2023 Not Ready for Inspection JOHNNY MIRANDA
Rough 9/25/2023 Not Ready for Inspection JOHNNY MIRANDA
Bottom/Toe 10/3/2023 Not Ready for Inspection JOHNNY MIRANDA
Bottom/Toe 10/16/2023 Approved RUSSELL BONVOULOIR
Final 10/16/2023 Not Ready for Inspection RUSSELL BONVOULOIR
Rough 10/16/2023 Approved RUSSELL BONVOULOIR
Final 10/19/2023 Permit Finaled JOHNNY MIRANDA