5262 N CLEON AVE 1-15 91601
Certificate Information: 5262 N CLEON AVE 1-15 91601
- Application / Permit
- 21030-10000-08483
- Plan Check / Job No.
- B21VN15643
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- Grading permit for new building R&R and site grading.
- Permit Issued
- Issued on 7/16/2024
- Issuing Office
- Current Status
- Permit Finaled on 2/23/2026
Permit Application Status History
| Submitted | 11/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2021 | RODOLFO ARIAS |
| Corrections Issued | 11/21/2021 | RODOLFO ARIAS |
| Quality Review Completed | 11/23/2021 | EUGENE BARBEAU |
| Applicant returned to address corrections | 8/19/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 10/6/2023 | RODOLFO ARIAS |
| Applicant returned to address corrections | 11/22/2023 | RODOLFO ARIAS |
| Plan Check Approved | 5/7/2024 | RODOLFO ARIAS |
| Issued | 7/16/2024 | APPLICANT |
| Permit Finaled | 2/20/2026 | MATTHEW JENKINS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/22/2021 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 8/22/2023 | AMMAR ELTAWIL |
Contact Information
| Contractor | Dotz Inc; Lic. No.: 1033830-B | , |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| MATTHEW JENKINS, (818) 374-4357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Bottom/Toe | 7/23/2024 | Partial Approval | MANUEL TEJADA |
| Excavation | 7/23/2024 | Partial Approval | MANUEL TEJADA |
| Bottom/Toe | 8/2/2024 | Approved | MANUEL TEJADA |
| Excavation | 8/2/2024 | Approved | MANUEL TEJADA |
| Fill/Backfill | 8/2/2024 | Approved | MANUEL TEJADA |
| Initial Grading | 8/2/2024 | Approved | MANUEL TEJADA |
| Approved Compaction Report | 8/13/2024 | Not Ready for Inspection | MANUEL TEJADA |
| Excavation | 8/13/2024 | Not Ready for Inspection | MANUEL TEJADA |
| Initial Grading | 8/13/2024 | Not Ready for Inspection | MANUEL TEJADA |
| Approved Compaction Report | 9/6/2024 | Approved | MANUEL TEJADA |
| Final | 2/20/2026 | Permit Finaled | MATTHEW JENKINS |
| Rough | 2/20/2026 | Approved | MATTHEW JENKINS |