5261 N HARMONY AVE 91601
Certificate Information: 5261 N HARMONY AVE 91601
- Application / Permit
- 21030-10000-07570
- Plan Check / Job No.
- B21LA21008
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- Grading permit to remove and recompaction for two duplexs and a single family dwewlling.
- Permit Issued
- Issued on 5/3/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 12/13/2023
Permit Application Status History
| Submitted | 2/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/5/2022 | ERIC WONG |
| Plan Check Approved | 4/20/2022 | ERIC WONG |
| Building Plans Picked Up | 5/2/2022 | APPLICANT |
| Issued | 5/3/2022 | APPLICANT |
| Permit Finaled | 12/12/2023 | MANUEL TEJADA |
Permit Application Clearance Information
| Address approval | Cleared | 4/13/2022 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 4/13/2022 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 4/13/2022 | LEE GUILBEAUX |
Contact Information
| Contractor | Sunny Construction & Development Corporation; Lic. No.: 737977-B | 711 S FIRST AVE ARCADIA, CA 91006 |
| Engineer | Jones,, Ryan Keith; Lic. No.: GE2852 | 1253 W MASLINE ST COVINA, CA 91722 |
| Engineer | Jong,, Hank Hsing-Lian; Lic. No.: C45846 | 11819 GOLDRING ROAD UNIT A ARCADIA, CA 91006 |
Inspector Information
| MATTHEW JENKINS, (818) 374-4357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 5/12/2022 | Approved | MANUEL TEJADA |
| Bottom/Toe | 5/18/2022 | Partial Approval | MANUEL TEJADA |
| Bottom/Toe | 5/27/2022 | Approved | MANUEL TEJADA |
| Excavation | 5/27/2022 | Approved | MANUEL TEJADA |
| Drainage Devices/Catch Basin | 6/13/2023 | Partial Inspection | MANUEL TEJADA |
| Rough | 6/15/2023 | Approved | MANUEL TEJADA |
| Drainage Devices/Catch Basin | 7/11/2023 | Partial Approval | MANUEL TEJADA |
| Sub-Drain | 7/11/2023 | Partial Approval | MANUEL TEJADA |
| Drainage Devices/Catch Basin | 8/14/2023 | Partial Approval | MANUEL TEJADA |
| Sub-Drain | 8/28/2023 | Partial Approval | ROBERT PINA |
| Final | 12/12/2023 | Permit Finaled | MANUEL TEJADA |