233 S ROCKINGHAM AVE 90049
Certificate Information: 233 S ROCKINGHAM AVE 90049
- Application / Permit
- 21030-10000-07383
- Plan Check / Job No.
- B21LA20475
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- SITE GRADING FOR NEW SFD
- Permit Issued
- Issued on 5/6/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 4/14/2026
Permit Application Status History
| Submitted | 10/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2021 | JOE VO |
| Corrections Issued | 11/27/2021 | JOE VO |
| Quality Review Completed | 12/14/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 3/14/2022 | JOE VO |
| Building Plans Picked Up | 3/15/2022 | APPLICANT |
| Plan Check Approved | 5/4/2022 | JOE VO |
| Issued | 5/6/2022 | APPLICANT |
| Permit Finaled | 4/14/2026 | JESUS RODRIGUEZ |
Permit Application Clearance Information
| Miscellaneous | Cleared | 4/21/2022 | JOE VO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| RUSSELL BONVOULOIR, (310) 914-3899 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 6/8/2022 | Approved | TIMOTHY POWELL |
| Excavation | 6/10/2022 | Not Ready for Inspection | TIMOTHY POWELL |
| Bottom/Toe | 6/14/2022 | Partial Inspection | TIMOTHY POWELL |
| Excavation | 6/14/2022 | Partial Inspection | TIMOTHY POWELL |
| Bottom/Toe | 6/16/2022 | Partial Inspection | TIMOTHY POWELL |
| Excavation | 6/16/2022 | Partial Inspection | TIMOTHY POWELL |
| Approved Compaction Report | 12/14/2022 | Approved | TIMOTHY POWELL |
| Bottom/Toe | 12/23/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| Excavation | 12/23/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Excavation | 2/8/2023 | Partial Inspection | RUSSELL BONVOULOIR |
| Initial Grading | 5/23/2023 | Partial Inspection | RUSSELL BONVOULOIR |
| Drainage Devices/Catch Basin | 2/13/2024 | Partial Approval | JOHNNY MIRANDA |
| Drainage Devices/Catch Basin | 2/21/2024 | Partial Approval | JOHNNY MIRANDA |
| Excavation | 6/6/2024 | Partial Approval | JOHNNY MIRANDA |
| Bottom/Toe | 8/7/2024 | Approved | JOHNNY MIRANDA |
| Final | 8/7/2024 | Not Ready for Inspection | JOHNNY MIRANDA |
| Rough | 8/7/2024 | Approved | JOHNNY MIRANDA |
| Approved Compaction Report | 10/30/2025 | Corrections Issued | MATTHEW JENKINS |
| Approved Compaction Report | 2/23/2026 | Approved | JOHNNY MIRANDA |
| Final | 3/2/2026 | Not Ready for Inspection | LANNY MERRICK |
| Final | 4/14/2026 | Permit Finaled | JESUS RODRIGUEZ |