146 N ASHDALE AVE 90049

Certificate Information: 146 N ASHDALE AVE 90049

Application / Permit
21030-10000-07239
Plan Check / Job No.
B21LA20106
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
GRADING TO REPLACE EXISTING RETAINING WALL.
Permit Issued
Issued on 5/30/2023
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 10/16/2023

Permit Application Status History

Submitted 10/26/2021 APPLICANT
Assigned to Plan Check Engineer 11/9/2021 JOHNNY WU
Corrections Issued 11/17/2021 JOHNNY WU
Quality Review Completed 11/18/2021 FARUK SEZER
Building Plans Picked Up 11/23/2021 APPLICANT
Applicant returned to address corrections 7/6/2022 JOHNNY WU
Plan Check Approved 9/30/2022 JOHNNY WU
Issued 5/30/2023 APPLICANT
Permit Finaled 10/16/2023 CHARLES POWELL

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/2/2021 DINAH GARIN
Miscellaneous Cleared 7/14/2022 BIJAN ZADEH
Excavation more than 5-ft deep Cleared 9/30/2022 CALOSHA APPROVED
Grading Pre-Inspection Cleared 9/30/2022 JOHNNY WU
Miscellaneous Cleared 9/30/2022 JOHNNY WU

Contact Information

Contractor Owner-Builder       ,
Engineer Baad,, Katherine Firestone; Lic. No.: C64669 5232 ZAKON RD      TORRANCE, CA 90505
Engineer Barr,, Joseph Daniel; Lic. No.: C70708 1185 HERITAGE FARM RD      HICKORY, NC 28601
Engineer Guzman,, Martin; Lic. No.: C79193 4054 W 165TH STREET      LAWNDALE, CA 90260
Geologist Miller,, Jonathan Steven; Lic. No.: EG2391 24736 CALVERT STREET      WOODLAND HILLS, CA 91367

Inspector Information

GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation 6/22/2023 Partial Approval CHARLES POWELL
Initial Grading 6/22/2023 Approved CHARLES POWELL
Deputy Other (see comments) 6/28/2023 Approved CHARLES POWELL
Excavation 7/13/2023 Partial Approval CHARLES POWELL
Deputy Other (see comments) 7/14/2023 Partial Approval CHARLES POWELL
Rough 7/21/2023 Partial Approval CHARLES POWELL
Rough 8/31/2023 Corrections Issued CHARLES POWELL
Approved Compaction Report 9/5/2023 Approved CHARLES POWELL
Bottom/Toe 9/13/2023 Approved CHARLES POWELL
Final 9/13/2023 Not Ready for Inspection CHARLES POWELL
Rough 9/13/2023 Not Ready for Inspection CHARLES POWELL
Final 10/16/2023 Permit Finaled CHARLES POWELL
Rough 10/16/2023 Approved CHARLES POWELL