9026 N WOODMAN AVE 91331
Certificate Information: 9026 N WOODMAN AVE 91331
- Application / Permit
- 21030-10000-06699
- Plan Check / Job No.
- B21LA18691
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- Recompaction and removal of Grading work for proposed Coin Laudry Building.
- Permit Issued
- Issued on 10/15/2021
- Issuing Office
- Current Status
- Permit Finaled on 12/20/2023
Permit Application Status History
| Submitted | 10/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/5/2021 | ZAW HAN |
| Plan Check Approved | 10/15/2021 | ZAW HAN |
| Issued | 10/15/2021 | APPLICANT |
| Permit Finaled | 12/20/2023 | BRIAN MILLER |
Permit Application Clearance Information
| ZA Case | Cleared | 10/6/2021 | DANIEL CORONADO |
Contact Information
| Contractor | Ubcon Inc; Lic. No.: 1058343-B | 3055 WILSHIRE BLVD #810 LOS ANGELES, CA 90010 |
| Engineer | Kim,, Hosang; Lic. No.: C67288 | 18759 WILLOWTREE LANE PORTER RANCH, CA 91326 |
| Engineer | Woo,, David Yungha; Lic. No.: C59736 | 9 CHAPARRAL CT RANCHO SANTA MARGARITA, CA 92688 |
Inspector Information
| ALEXANDER HELFER, (818) 374-4354 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 10/20/2021 | Approved | TIMOTHY POWELL |
| Excavation | 10/20/2021 | Partial Approval | TIMOTHY POWELL |
| Initial Grading | 10/20/2021 | Approved | TIMOTHY POWELL |
| Deputy Grading | 10/27/2021 | Approved | TIMOTHY POWELL |
| Fill/Backfill | 10/27/2021 | Partial Approval | TIMOTHY POWELL |
| Deputy Grading | 10/28/2021 | Approved | BRIAN MILLER |
| Deputy Grading | 10/29/2021 | Approved | BRIAN MILLER |
| Fill/Backfill | 10/29/2021 | Partial Approval | BRIAN MILLER |
| Approved Compaction Report | 12/3/2021 | Approved | BRIAN MILLER |
| Drainage Devices/Catch Basin | 4/28/2023 | Partial Approval | MANUEL TEJADA |
| Sub-Drain | 4/28/2023 | Partial Approval | MANUEL TEJADA |
| Bottom/Toe | 12/13/2023 | Approved | BRIAN MILLER |
| Final | 12/13/2023 | Corrections Issued | BRIAN MILLER |
| Rough | 12/13/2023 | Approved | BRIAN MILLER |
| Approved Compaction Report | 12/19/2023 | Approved | BRIAN MILLER |
| Final | 12/20/2023 | Permit Finaled | BRIAN MILLER |