74 S BEVERLY PARK LANE 90210

Certificate Information: 74 S BEVERLY PARK LANE 90210

Application / Permit
21030-10000-06172
Plan Check / Job No.
B21LA17325
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
BACKFILL BASEMENT AREA AFTER DEMO IS COMPLETE. CUT AND FILL= 2625 YARDS; NO IMPORT OR EXPORT, MAX 5' VERTICAL EXCAVATION. CUT AND FILL ONLY ON DISTURBED LAND
Permit Issued
Issued on 2/9/2022
Issuing Office
Current Status
Permit Finaled on 5/10/2022

Permit Application Status History

Submitted 9/20/2021 APPLICANT
Assigned to Plan Check Engineer 9/22/2021 SINA KHOSRAVI
Corrections Issued 9/28/2021 SINA KHOSRAVI
Applicant returned to address corrections 12/1/2021 AUNG SOE
Applicant returned to address corrections 12/14/2021 FERNANDO FLORES
Issued 2/9/2022 APPLICANT
Building Plans Picked Up 2/10/2022 APPLICANT
Permit Finaled 5/10/2022 ALEXANDER HELFER

Permit Application Clearance Information

ZA Case Cleared 10/8/2021 JASON CHAN
ZA Case Cleared 10/8/2021 JASON CHAN
ZA Case Cleared 10/8/2021 JASON CHAN
ZA Case Cleared 10/8/2021 JASON CHAN
ZA Case Cleared 10/8/2021 JASON CHAN
ZA Case Cleared 10/8/2021 JASON CHAN
ZA Case Cleared 10/8/2021 JASON CHAN
Grading Pre-Inspection Cleared 12/13/2021 SINA KHOSRAVI
Specific Plan Cleared 1/20/2022 OLGA AYALA
GPI Written Notices Cleared 2/1/2022 SINA KHOSRAVI

Contact Information

Contractor Owner-Builder       ,
Engineer , ; Lic. No.: C93123 889 PIERCE COURT   SUITE 101    THOUSAND OAKS, CA 91360

Inspector Information

ROBERT PINA, (213) 482-0404 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Bottom/Toe 2/16/2022 Approved ALEXANDER HELFER
Approved Compaction Report 5/4/2022 Approved ALEXANDER HELFER
Approved Compaction Report 5/5/2022 Partial Inspection MATTHEW JENKINS
Final 5/5/2022 Partial Inspection MATTHEW JENKINS
Rough 5/5/2022 Partial Inspection MATTHEW JENKINS
Final 5/10/2022 Permit Finaled ALEXANDER HELFER
Rough 5/10/2022 Approved ALEXANDER HELFER