12450 W MILLENNIUM 90094
Certificate Information: 12450 W MILLENNIUM 90094
- Application / Permit
- 21030-10000-06068
- Plan Check / Job No.
- B21LA16857
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- GRADING FOR NEW PARKING LOT 3 OF 3
- Permit Issued
- Issued on 5/10/2022
- Issuing Office
- Current Status
- Permit Finaled on 9/23/2022
Permit Application Status History
| Submitted | 9/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2021 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 10/15/2021 | FARSHAD ALIMOHAMADI |
| Quality Review Completed | 10/21/2021 | SAI KHUM |
| Applicant returned to address corrections | 1/11/2022 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 2/23/2022 | FARSHAD ALIMOHAMADI |
| Disabled Access Plans Picked Up | 4/12/2022 | APPLICANT |
| Plan Check Approved | 4/27/2022 | FARSHAD ALIMOHAMADI |
| Issued | 5/10/2022 | APPLICANT |
| Permit Finaled | 9/22/2022 | JONATHAN HOM |
| Building Plans Picked Up | 5/20/2023 | APPLICANT |
Permit Application Clearance Information
| Low Impact Development | Cleared | 10/19/2021 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 11/4/2021 | HISASHI KOBAYAKAWA |
| Miscellaneous | Cleared | 11/5/2021 | MAXFIELD VERMY |
| Miscellaneous | Cleared | 11/5/2021 | MAXFIELD VERMY |
| Specific Plan | Cleared | 11/5/2021 | MAXFIELD VERMY |
| ZA Case | Cleared | 11/5/2021 | MAXFIELD VERMY |
| Eng Process Fee Ord 176,300 | Cleared | 11/8/2021 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | Whiting-Turner Contracting Company The; Lic. No.: 311107-B | 800 R STREET SACRAMENTO, CA 95811 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| JESUS RODRIGUEZ, (213) 216-1187 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation | 5/12/2022 | Partial Inspection | JONATHAN HOM |
| Initial Grading | 5/12/2022 | Approved | JONATHAN HOM |
| Bottom/Toe | 5/16/2022 | Not Ready for Inspection | AL GAMBLE |
| Bottom/Toe | 5/18/2022 | Partial Approval | JONATHAN HOM |
| Deputy Grading | 5/20/2022 | Approved | JONATHAN HOM |
| Rough | 5/23/2022 | Partial Approval | JONATHAN HOM |
| Bottom/Toe | 5/24/2022 | Not Ready for Inspection | JONATHAN HOM |
| Deputy Grading | 5/25/2022 | Approved | TIMOTHY POWELL |
| Excavation | 5/25/2022 | Partial Approval | TIMOTHY POWELL |
| Deputy Grading | 5/26/2022 | Approved | TIMOTHY POWELL |
| Deputy Grading | 5/27/2022 | Conditional Approval | MATTHEW JENKINS |
| Bottom/Toe | 6/1/2022 | Partial Approval | JONATHAN HOM |
| Drainage Devices/Catch Basin | 6/10/2022 | Partial Approval | AL GAMBLE |
| Sub-Drain | 6/10/2022 | Partial Approval | AL GAMBLE |
| Sub-Drain | 6/14/2022 | Partial Approval | MATTHEW JENKINS |
| Bottom/Toe | 6/16/2022 | Partial Approval | AL GAMBLE |
| Sub-Drain | 6/16/2022 | Partial Inspection | AL GAMBLE |
| Sub-Drain | 6/17/2022 | Partial Inspection | AL GAMBLE |
| Drainage Devices/Catch Basin | 6/29/2022 | Partial Approval | AL GAMBLE |
| Fill/Backfill | 6/29/2022 | Partial Approval | AL GAMBLE |
| Deputy Grading | 7/5/2022 | Approved | JONATHAN HOM |
| Bottom/Toe | 9/9/2022 | Not Ready for Inspection | JONATHAN HOM |
| Final | 9/9/2022 | Not Ready for Inspection | JONATHAN HOM |
| Rough | 9/9/2022 | Not Ready for Inspection | JONATHAN HOM |
| Approved Compaction Report | 9/20/2022 | Approved | JONATHAN HOM |
| Bottom/Toe | 9/22/2022 | Approved | JONATHAN HOM |
| Final | 9/22/2022 | Permit Finaled | JONATHAN HOM |
| Rough | 9/22/2022 | Approved | JONATHAN HOM |