1014 W VIA CORDOVA 90732
Certificate Information: 1014 W VIA CORDOVA 90732
- Application / Permit
- 21030-10000-05855
- Plan Check / Job No.
- B21LA16309
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- 2 OF 2 EXCAVATE AND BACKFILL FOR (N) RETAINING WALL
- Permit Issued
- Issued on 2/27/2024
- Issuing Office
- San Pedro
- Current Status
- Permit Finaled on 8/20/2025
Permit Application Status History
| Submitted | 2/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2022 | ADRIANA LOPEZ |
| Corrections Issued | 3/14/2022 | ADRIANA LOPEZ |
| Quality Review Completed | 3/16/2022 | SAI KHUM |
| Building Plans Picked Up | 3/18/2022 | APPLICANT |
| Applicant returned to address corrections | 10/20/2022 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 5/10/2023 | ADRIANA LOPEZ |
| Plan Check Approved | 6/29/2023 | ADRIANA LOPEZ |
| Issued | 2/27/2024 | APPLICANT |
| Permit Finaled | 8/19/2025 | MATTHEW JENKINS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/10/2023 | ADRIANA LOPEZ |
Contact Information
| Contractor | Lagmay Corporation; Lic. No.: 579368-B | 59 PASEO DE CASTANA RANCHO PALOS VERDES, CA 90275 |
| Engineer | Arca,, Perfecto; Lic. No.: C28918 | 23222 ROSANNA COURT TORRANCE, CA 90502 |
| Engineer | Lin,, Chi Hsin; Lic. No.: GE2921 | 123 N VALENCIA ST ALHAMBRA, CA 91801 |
Inspector Information
| JESUS RODRIGUEZ, (213) 216-1187 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation | 10/9/2024 | Corrections Issued | AL GAMBLE |
| Excavation | 10/11/2024 | Corrections Issued | AL GAMBLE |
| Excavation | 11/4/2024 | Not Ready for Inspection | AL GAMBLE |
| Excavation | 11/6/2024 | Partial Inspection | AL GAMBLE |
| Excavation | 11/12/2024 | Partial Inspection | MATTHEW JENKINS |
| Excavation | 2/10/2025 | Partial Inspection | MATTHEW JENKINS |
| Excavation | 2/20/2025 | Partial Approval | MATTHEW JENKINS |
| Special/Order Compliance | 2/25/2025 | Not Ready for Inspection | AL GAMBLE |
| Special/Order Compliance | 2/27/2025 | Partial Inspection | AL GAMBLE |
| Special/Order Compliance | 2/28/2025 | Partial Approval | MATTHEW JENKINS |
| Rough | 3/3/2025 | Partial Inspection | MATTHEW JENKINS |
| Sub-Drain | 3/10/2025 | Not Ready for Inspection | AL GAMBLE |
| Drainage Devices/Catch Basin | 3/12/2025 | Partial Approval | MATTHEW JENKINS |
| Drainage Devices/Catch Basin | 4/1/2025 | Not Ready for Inspection | MATTHEW JENKINS |
| Approved Compaction Report | 8/14/2025 | Approved | MATTHEW JENKINS |
| Bottom/Toe | 8/19/2025 | Approved | MATTHEW JENKINS |
| Final | 8/19/2025 | Permit Finaled | MATTHEW JENKINS |