2225 W SUNSET BLVD 90026
Certificate Information: 2225 W SUNSET BLVD 90026
- Application / Permit
- 21030-10000-05789
- Plan Check / Job No.
- B21LA16109
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (70) Grading - Hillside
- Work Description
- Grading permit for new apartment/basement excavation, retaining wall backfill and site grading. Board File 210079 APPROVED FOR AN EXPORT OF 47,000 CUBIC YARDS
- Permit Issued
- Issued on 8/18/2022
- Issuing Office
- Metro
- Current Status
- Issued on 8/18/2022
Permit Application Status History
| Submitted | 8/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2021 | RODOLFO ARIAS |
| Green Plans Picked Up | 9/10/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 9/15/2021 | APPLICANT |
| Corrections Issued | 9/24/2021 | RODOLFO ARIAS |
| Quality Review Completed | 9/28/2021 | EUGENE BARBEAU |
| Applicant returned to address corrections | 10/27/2021 | RODOLFO ARIAS |
| Applicant returned to address corrections | 12/9/2021 | RODOLFO ARIAS |
| Applicant returned to address corrections | 1/11/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 1/20/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 1/27/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 2/1/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 2/8/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 2/11/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 3/4/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 3/9/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 4/7/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 6/8/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 6/10/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 6/24/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 7/8/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 7/13/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 8/12/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 8/17/2022 | RODOLFO ARIAS |
| Plan Check Approved | 8/18/2022 | RODOLFO ARIAS |
| Issued | 8/18/2022 | APPLICANT |
Permit Application Clearance Information
| DCP conditions approval | Cleared | 4/6/2022 | JAMES MCCARTHY |
| "Q" conditions | Cleared | 4/19/2022 | RUBEN VASQUEZ |
| CPC | Cleared | 4/19/2022 | RUBEN VASQUEZ |
| Tract Map conditions | Cleared | 4/19/2022 | RUBEN VASQUEZ |
| Tract Map conditions | Cleared | 4/19/2022 | RUBEN VASQUEZ |
| Trees in Parkway | Cleared | 5/13/2022 | ADALBERTO VERA |
| Construction near power lines | Cleared | 6/27/2022 | WALTER RAMIREZ |
| Permit | Cleared | 6/27/2022 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 6/27/2022 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 7/1/2022 | CELINA MORENO |
| Work Adjacent to Public Way | Cleared | 7/8/2022 | JOSE RODRIGUEZ |
| Excavation more than 5-ft deep | Cleared | 8/4/2022 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 8/4/2022 | RODOLFO ARIAS |
| Grading Pre-Inspection | Cleared | 8/4/2022 | RODOLFO ARIAS |
| Haul Route | Cleared | 8/12/2022 | KARL MUHS |
Contact Information
| Contractor | Integrare Group Llc; Lic. No.: 1063352-B | 12421 VENICE BLVD LOS ANGELES, CA 90066 |
| Engineer | Cefali,, David Allen; Lic. No.: S3658 | 4344 LAUREL CANYON BLVD_STE 3 STUDIO CITY, CA 91604 |
| Engineer | Davis,, Richard Hays; Lic. No.: C48082 | 2015 CANTATA DR LOS ANGELES, CA 90068 |
| Engineer | Fiorelli,, Diane M; Lic. No.: GE3042 | 318 N WINNIPEG PLACE LONG BEACH, CA 90814 |
| Engineer | Riutort,, Enrique Alfonso; Lic. No.: GE2683 | 3087 N PINEWOOD ST ORANGE, CA 92865 |
| Geologist | Wilkins,, Shaun Hunter; Lic. No.: EG2665 | 1716 N GLENVIEW AVE ANAHEIM HILLS, CA 92807 |
Inspector Information
| RAMAZANALI ALMASI, (213) 482-0398 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation | 8/19/2022 | Not Ready for Inspection | ROBERT HUGHES |
| Initial Grading | 8/19/2022 | Corrections Issued | ROBERT HUGHES |
| Deputy Grading | 8/22/2022 | Approved | ROBERT HUGHES |
| Deputy Grading | 8/23/2022 | Approved | ROBERT HUGHES |
| Excavation | 8/23/2022 | Partial Approval | ROBERT HUGHES |
| Deputy Grading | 8/24/2022 | Approved | ROBERT HUGHES |
| Deputy Grading | 8/25/2022 | Approved | ROBERT HUGHES |
| Fill/Backfill | 8/25/2022 | Partial Approval | ROBERT HUGHES |
| Deputy Grading | 8/26/2022 | Approved | ROBERT HUGHES |
| Excavation | 9/6/2022 | Not Ready for Inspection | ROBERT HUGHES |
| Excavation | 12/7/2022 | Not Ready for Inspection | ROBERT HUGHES |
| Drainage Devices/Catch Basin | 2/7/2023 | Not Ready for Inspection | ALEXANDER HELFER |
| Sub-Drain | 2/7/2023 | Not Ready for Inspection | ALEXANDER HELFER |
| Sub-Drain | 3/10/2023 | Partial Approval | LANNY MERRICK |
| Sub-Drain | 4/12/2023 | Approved | ALEXANDER HELFER |
| Sub-Drain | 5/24/2023 | Partial Approval | LANNY MERRICK |
| Fill/Backfill | 6/16/2023 | Not Ready for Inspection | ALEXANDER HELFER |
| Drainage Devices/Catch Basin | 5/14/2024 | Not Ready for Inspection | ALEXANDER HELFER |
| Rough | 5/14/2024 | Not Ready for Inspection | ALEXANDER HELFER |
| Drainage Devices/Catch Basin | 11/19/2025 | Partial Approval | RUSSELL BONVOULOIR |
| Sub-Drain | 12/9/2025 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Sub-Drain | 12/10/2025 | Partial Approval | RAMAZANALI ALMASI |