5461 N LOUISE AVE 91316

Certificate Information: 5461 N LOUISE AVE 91316

Application / Permit
21030-10000-05483
Plan Check / Job No.
B21LA15387
Group
Building
Type
Grading
Sub-Type
Commercial
Primary Use
(60) Grading - Non-Hillside
Work Description
GRADING FOR NEW SCHOOL BUILDING "LOWER SCHOOL" ON (E) CAMPUS (2 OF 2)
Permit Issued
Issued on 7/8/2022
Issuing Office
Metro
Current Status
Permit Finaled on 2/8/2024

Permit Application Status History

Submitted 8/18/2021 APPLICANT
Assigned to Plan Check Engineer 9/9/2021 FARSHAD ALIMOHAMADI
Corrections Issued 10/7/2021 FARSHAD ALIMOHAMADI
Quality Review Completed 10/7/2021 SAI KHUM
Applicant returned to address corrections 12/21/2021 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 12/22/2021 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 12/23/2021 FARSHAD ALIMOHAMADI
Building Plans Picked Up 12/23/2021 APPLICANT
Applicant returned to address corrections 12/29/2021 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 1/18/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 2/1/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 2/10/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 2/17/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 3/17/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 6/7/2022 FARSHAD ALIMOHAMADI
Plan Check Approved 7/5/2022 FARSHAD ALIMOHAMADI
Issued 7/8/2022 APPLICANT
Permit Finaled 2/8/2024 ROBERT PINA

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/14/2021 LEE GUILBEAUX
Miscellaneous Cleared 10/14/2021 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 10/14/2021 LEE GUILBEAUX
Low Impact Development Cleared 6/30/2022 JORGE MEJIA LEMUS

Contact Information

Contractor Suffolk Construction Company Inc; Lic. No.: 751099-B 525 MARKET STREET   SUITE 2850    SAN FRANCISCO, CA 94105

Inspector Information

MANUEL TEJADA, (818) 374-4339 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation 8/12/2022 Partial Approval LANNY MERRICK
Bottom/Toe 10/6/2022 Not Ready for Inspection LANNY MERRICK
Final 10/6/2022 Not Ready for Inspection LANNY MERRICK
Rough 10/6/2022 Not Ready for Inspection LANNY MERRICK
Approved Compaction Report 10/27/2022 Approved VASIL MIHALEV
Rough 10/27/2022 Approved VASIL MIHALEV
Approved Compaction Report 11/9/2022 Approved VASIL MIHALEV
Sub-Drain 12/9/2022 Partial Approval VASIL MIHALEV
Sub-Drain 12/10/2022 Off-Hour Fees Due
Bottom/Toe 1/30/2023 Partial Approval MANUEL TEJADA
Drainage Devices/Catch Basin 3/8/2023 Partial Approval MANUEL TEJADA
Fill/Backfill 3/8/2023 Partial Approval MANUEL TEJADA
Drainage Devices/Catch Basin 3/9/2023 Partial Approval MANUEL TEJADA
Bottom/Toe 3/14/2023 Not Ready for Inspection MANUEL TEJADA
Sub-Drain 3/14/2023 Not Ready for Inspection MANUEL TEJADA
Drainage Devices/Catch Basin 3/16/2023 Partial Approval MANUEL TEJADA
Sub-Drain 3/29/2023 Partial Approval MANUEL TEJADA
Excavation 4/17/2023 Partial Approval MICHAEL TEMPLE
Initial Grading 4/19/2023 Not Ready for Inspection ROBERT PINA
Drainage Devices/Catch Basin 10/13/2023 Partial Approval MANUEL TEJADA
Bottom/Toe 10/18/2023 Not Ready for Inspection ROBERT PINA
Final 10/18/2023 Not Ready for Inspection ROBERT PINA
Approved Compaction Report 11/7/2023 Approved MANUEL TEJADA
Final 11/20/2023 Not Ready for Inspection ROBERT PINA
Bottom/Toe 2/8/2024 Approved ROBERT PINA
Final 2/8/2024 Permit Finaled ROBERT PINA